SOLAR · PJMBartonsville Energy Facility
Bartonsville Energy Facility is a 40.0 MW solar request withdrawn in the PJM interconnection queue, in Frederick County, Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedOct 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-533
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Bartonsville-Meadowbrook 138 kV IV
- Location
- Frederick County, Virginia
- Technology
- Solar: 40.0 MW
- Total requested
- 40.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 September 2020
- Proposed online date
- December 2023
- Withdrawn
- October 2024
Location
Marker shows the centre of Frederick County; the queue data does not give exact sites.
Other requests in Frederick County
- Solar project AG2-182, Frederick CountySolar · 200 MW · in study
- Battery storage project AG2-288, Frederick CountyBattery storage · 150 MW · in study
- Battery storage project AI1-184, Frederick CountyBattery storage · 110 MW · in study
- Battery storage project AG2-300, Frederick CountyBattery storage · 100 MW · in study
- Redbud-Gaylord 34.5 kVSolar · 30.0 MW · suspended
- Foxglove SolarSolar · 75.0 MW · built
- Bartonsville Energy FacilitySolar · 70.0 MW · built
- Bartonsville Energy FacilitySolar · 50.0 MW · built
- Bartonsville Energy FacilitySolar · 10.0 MW · built
- Fredrick County Regional LFOther · 2.0 MW · built
- Solar + storage project AH1-119, Frederick CountySolar + storage · 100 MW · withdrawn
- Solar + storage project AG2-584, Frederick CountySolar + storage · 90.0 MW · withdrawn