United States › Grid › Interconnection queues › Virginia
BATTERY STORAGE · PJMScout Energy Storage
Scout Energy Storage is a 40.0 MW battery storage request withdrawn in the PJM interconnection queue, in Accomack County, Virginia, connecting to DPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2020 (completed)
- Withdrawn / abandonedNov 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-061
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Connection point (POI)
- Wattsville 69kV
- Location
- Accomack County, Virginia
- Technology
- Battery: 40.0 MW
- Total requested
- 40.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 24 January 2020
- Proposed online date
- June 2021
- Withdrawn
- November 2024
Location
Marker shows the centre of Accomack County; the queue data does not give exact sites.
Other requests in Accomack County
- Battery storage project AH2-050, Accomack CountyBattery storage · 20.0 MW · in study
- Switchgrass Solar 1Solar · 49.0 MW · suspended
- Switchgrass Solar 1Solar · 20.0 MW · suspended
- Scout Storage IBattery storage · 9.0 MW · suspended
- TasleyOther · 6.7 MW · built
- Solar project AD2-032, Accomack CountySolar · 150 MW · withdrawn
- Solar project AE2-328, Accomack CountySolar · 100 MW · withdrawn
- Solar project AG2-258, Accomack CountySolar · 100 MW · withdrawn
- Onshore wind project Y1-029, Accomack CountyOnshore wind · 99.0 MW · withdrawn
- Onshore wind project W3-054A, Accomack CountyOnshore wind · 95.0 MW · withdrawn
- Solar project AE2-233, Accomack CountySolar · 94.0 MW · withdrawn
- Solar project AE1-073, Accomack CountySolar · 75.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem