Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown31485.5 GW
Active in queue17.0 GW93 requests
Agreement signed1,847 MW16 requests
Withdrawn31485.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

314 requests · page 5 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2940, Sharkey County
Solar
100 MWWithdrawn / abandoned Sharkey, MSMISO Sep 2022target 2025
Solar project J2741, Sunflower County
Solar
100 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2022target 2026
Solar project 307, Lowndes County
Solar
100 MWWithdrawn / abandoned Lowndes, MSSoutheast Jan 2017
Battery storage project 433, Clay County
Battery storage
100 MWWithdrawn / abandoned Clay, MSSoutheast May 2020target 2023
Solar project IC-923, Pearl River County
Solar
100 MWWithdrawn / abandoned Pearl River, MSSoutheast Dec 2020
Solar project J3150, Panola County
Solar
100 MWWithdrawn / abandoned Panola, MSMISO Sep 2022target 2027
Solar + storage project J2905, Washington County
Solar + storage
100 MWWithdrawn / abandoned Washington, MSMISO Sep 2022target 2025
Solar project J3772, Panola County
Solar
100 MWWithdrawn / abandoned Panola, MSMISO Apr 2024target 2028
Solar project J1136, Hinds County
Solar
100 MWWithdrawn / abandoned Hinds, MSMISO Mar 2018target 2021
Solar project J2428, Coahoma County
Solar
100 MWWithdrawn / abandoned Coahoma, MSMISO Sep 2022target 2026
Solar project 664, Chickasaw County
Solar
100 MWWithdrawn / abandoned Chickasaw, MSSoutheast Oct 2024
Solar project J2370, Hinds County
Solar
100 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2024
Solar project IC-1184, Wayne County
Solar
100 MWWithdrawn / abandoned Wayne, MSSoutheast Oct 2023target 2027
Solar project IC-683, Jones County
Solar
100 MWWithdrawn / abandoned Jones, MSSoutheast Mar 2018
Solar project IC-922, Newton County
Solar
100 MWWithdrawn / abandoned Newton, MSSoutheast Dec 2020target 2025
Solar project J2391, Tallahatchie County
Solar
100 MWWithdrawn / abandoned Tallahatchie, MSMISO Sep 2022target 2026
Solar project J2162, Leflore County
Solar
100 MWWithdrawn / abandoned Leflore, MSMISO Aug 2021target 2024
Solar + storage project 529, Rankin County
Solar + storage
100 MWWithdrawn / abandoned Rankin, MSSoutheast Jan 2023target 2026
Solar project J585, Madison County
Solar
100 MWWithdrawn / abandoned Madison, MSMISO May 2016target 2016
Solar project J588, Panola County
Solar
100 MWWithdrawn / abandoned Panola, MSMISO May 2016target 2018
Solar project J2980, Perry County
Solar
100 MWWithdrawn / abandoned Perry, MSMISO Sep 2022target 2023
Solar project J1070, Washington County
Solar
100 MWWithdrawn / abandoned Washington, MSMISO Mar 2018target 2021
Solar project J1157, Hinds County
Solar
100 MWWithdrawn / abandoned Hinds, MSMISO Mar 2018target 2020
Solar project J2182, Tallahatchie County
Solar
100 MWWithdrawn / abandoned Tallahatchie, MSMISO Aug 2021target 2025
Other project IC-245, Clarke County
Other
100 MWWithdrawn / abandoned Clarke, MSSoutheast Dec 2010
Solar project J3806, Sunflower County
Solar
100 MWWithdrawn / abandoned Sunflower, MSMISO Apr 2024target 2028
Solar + storage project J2825, Panola County
Solar + storage
100 MWWithdrawn / abandoned Panola, MSMISO Sep 2022target 2025
Solar project IC-690, Jones County
Solar
100 MWWithdrawn / abandoned Jones, MSSoutheast Mar 2018
Solar + storage project J2771, Coahoma County
Solar + storage
100 MWWithdrawn / abandoned Coahoma, MSMISO Sep 2022target 2027
Solar project J3714, Scott County
Solar
95.0 MWWithdrawn / abandoned Scott, MSMISO Apr 2024target 2028
Solar project J2023, Amite County
Solar
94.1 MWWithdrawn / abandoned Amite, MSMISO Aug 2021target 2024
Battery storage project J2015, Tunica County
Battery storage
90.0 MWWithdrawn / abandoned Tunica, MSMISO Aug 2021target 2025
Solar project J2745, Humphreys County
Solar
90.0 MWWithdrawn / abandoned Humphreys, MSMISO Sep 2022target 2026
Solar project J1957, Coahoma County
Solar
90.0 MWWithdrawn / abandoned Coahoma, MSMISO Nov 2021target 2025
Solar project J1113, Sunflower County
Solar
85.0 MWWithdrawn / abandoned Sunflower, MSMISO Mar 2018target 2022
Solar project J3104, Hinds County
Solar
85.0 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2027
Solar project J3542, Lincoln County
Solar
80.0 MWWithdrawn / abandoned Lincoln, MSMISO Apr 2024target 2028
Solar project IC-936, Pearl River County
Solar
80.0 MWWithdrawn / abandoned Pearl River, MSSoutheast Dec 2020
Solar + storage project 25-IC-1335, Perry County
Solar + storage
80.0 MWWithdrawn / abandoned Perry, MSSoutheast Apr 2025
Battery storage project J3177, Tunica County
Battery storage
80.0 MWWithdrawn / abandoned Tunica, MSMISO Sep 2022target 2026
Other project 242, Noxubee County
Other
80.0 MWWithdrawn / abandoned Noxubee, MSSoutheast Nov 2013
Solar project IC-576, Clarke County
Solar
80.0 MWWithdrawn / abandoned Clarke, MSSoutheast Jan 2017
Surplus; J1294
Other
80.0 MWWithdrawn / abandoned Sunflower, MSMISO Apr 2024target 2026
Solar project J3205, Franklin County
Solar
80.0 MWWithdrawn / abandoned Franklin, MSMISO Sep 2022target 2027
Solar project 285, Lowndes County
Solar
80.0 MWWithdrawn / abandoned Lowndes, MSSoutheast Mar 2016
Solar project IC-1028, Greene County
Solar
80.0 MWWithdrawn / abandoned Greene, MSSoutheast Mar 2022
Solar project J2313, Sunflower County
Solar
80.0 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2021target 2023
Solar project IC-1021, Lamar County
Solar
80.0 MWWithdrawn / abandoned Lamar, MSSoutheast Feb 2022
Solar project IC-673, George County
Solar
79.7 MWWithdrawn / abandoned George, MSSoutheast Feb 2018
Solar project IC-475, Hancock County
Solar
78.6 MWWithdrawn / abandoned Hancock, MSSoutheast Jul 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)