πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

SOLAR + STORAGE Β· MISO

Solar + storage project J2825, Panola County

Solar + storage project J2825, Panola County is a 100 MW solar + storage request withdrawn in the MISO interconnection queue, in Panola County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2825
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
COMO - CRENSHAW 115kV
Location
Panola County, Mississippi
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
13 September 2022
Proposed online date
March 2025
Withdrawn
July 2025

Location

Marker shows the centre of Panola County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Panola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem