SOLAR Β· SOUTHEAST

Solar project IC-922, Newton County

Solar project IC-922, Newton County is a 100 MW solar request withdrawn in the Southeast interconnection queue, in Newton County, Mississippi, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2020 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-922
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Collins - Newton 115 kV Line
Location
Newton County, Mississippi
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
18 December 2020
Proposed online date
January 2025
Withdrawn
September 2025

Location

Marker shows the centre of Newton County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Newton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem