Solar project IC-1244, Newton County

Solar project IC-1244, Newton County is a 100 MW solar request suspended in the Southeast interconnection queue, in Newton County, Mississippi, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued Mar 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-1244
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Newton - Forest Industrial 115 kV Line
Location
Newton County, Mississippi
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Queue status
Suspended
Entered queue
4 March 2024
Proposed online date
April 2029

Location

Marker shows the centre of Newton County; the queue data does not give exact sites.

Power plants in Mississippi · Transmission lines in Mississippi

Other requests in Newton County