🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Illinois — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown35863.7 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

358 requests · page 5 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3306, Perry County
Solar
150 MWIn study Perry, ILMISO Apr 2024target 2028
Battery storage project AH1-564, Winnebago County
Battery storage · Rockford Generation, LLC
150 MWIn study Winnebago, ILPJM Mar 2025target 2025
Solar project J1626, Fayette County
Solar
150 MWIn study Fayette, ILMISO Jun 2020target 2027
Battery storage project J2627, Adams County
Battery storage
150 MWIn study Adams, ILMISO Sep 2022target 2025
Solar + storage project J2797, White County
Solar + storage
150 MWIn study White, ILMISO Oct 2025target 2026
Solar project AH1-196, Mchenry County
Solar · Pleasant Grove Solar 2, LLC
150 MWIn study Mchenry, ILPJM Mar 2025target 2026
Osagrove Flats Solar
Solar · Aurora Solar LLC
150 MWIn study Lasalle, ILPJM Mar 2020target 2023
Onshore wind project J4007, Peoria County
Onshore wind
150 MWIn study Peoria, ILMISO May 2025target 2027
Otter Creek Solar
Solar · Aurora Solar LLC
150 MWIn study Lasalle, ILPJM Mar 2020target 2023
Plano Skies Energy Center
Solar · Plano Skies Energy Center, LLC
150 MWIn study Kendall, ILPJM Mar 2019target 2022
Solar project J2131, Jasper County
Solar
150 MWIn study Jasper, ILMISO Aug 2021target 2027
Solar + storage project J3185, Effingham County
Solar + storage
150 MWIn study Effingham, ILMISO Sep 2022target 2027
Solar + storage project J2151, Saline County
Solar + storage
150 MWIn study Saline, ILMISO Aug 2021target 2025
Solar project J1653, Tazewell County
Solar
150 MWIn study Tazewell, ILMISO Dec 2021target 2026
Battery storage project J3316, Washington County
Battery storage
150 MWIn study Washington, ILMISO May 2024target 2028
Solar project AH1-341, Ogle County
Solar · ibV Energy Partners LLC
150 MWIn study Ogle, ILPJM Mar 2025target 2025
Solar + storage project J3224, Marion County
Solar + storage
150 MWIn study Marion, ILMISO Sep 2022target 2026
Battery storage project J2203, Adams County
Battery storage
150 MWIn study Adams, ILMISO Mar 2022target 2024
Battery storage project J2170, Clark County
Battery storage
150 MWIn study Clark, ILMISO Apr 2022target 2024
Surplus; Shelby
Other
150 MWIn study Cumberland, ILMISO Jun 2024target 2026
Solar project J2156, Johnson County
Solar
150 MWIn study Johnson, ILMISO Jun 2022target 2024
Battery storage project J3695, Clark County
Battery storage
150 MWIn study Clark, ILMISO Apr 2024target 2028
Surplus
Battery storage
150 MWIn study St. Clair, ILMISO Jan 2025target 2029
Solar project J1744, Cumberland County
Solar
150 MWIn study Cumberland, ILMISO Apr 2022target 2027
Solar project J1651, Logan County
Solar
150 MWIn study Logan, ILMISO Jun 2020target 2023
Onshore wind project J1755, Bureau County
Onshore wind
147 MWIn study Bureau, ILMISO Jun 2020target 2025
Onshore wind project J3754, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Onshore wind project J3755, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Solar project AH2-085, Dekalb County
Solar
145 MWIn study Dekalb, ILPJM Jan 2022target 2026
Solar + storage project J3184, St. Clair County
Solar + storage
145 MWIn study St. Clair, ILMISO Sep 2022target 2027
Onshore wind project J2311, Putnam County
Onshore wind
145 MWIn study Putnam, ILMISO Oct 2024target 2024
Kankakee Solar
Solar · AEUG Kankakee Solar, LLC
144 MWIn study Kankakee, ILPJM Feb 2020target 2021
Battery storage project J3063, Perry County
Battery storage
143 MWIn study Perry, ILMISO Sep 2022target 2026
Solar + storage project J3004, Mason County
Solar + storage
142 MWIn study Mason, ILMISO Sep 2022target 2025
Solar project J3797, Edgar County
Solar
141 MWIn study Edgar, ILMISO Apr 2024target 2028
Solar project J3611, Hamilton County
Solar
140 MWIn study Hamilton, ILMISO Apr 2024target 2026
Solar project J2972, Adams County
Solar
140 MWIn study Adams, ILMISO Sep 2022target 2026
Onshore wind project J3918, Champaign County
Onshore wind
138 MWIn study Champaign, ILMISO Feb 2025target 2028
Surplus; J33/J734
Other
135 MWIn study Ford, ILMISO May 2023target 2026
Surplus; J734
Other
135 MWIn study Mclean, ILMISO Dec 2022target 2026
Solar + storage project J2648, Champaign County
Solar + storage
135 MWIn study Champaign, ILMISO Sep 2022target 2027
Onshore wind project AI2-390, Mclean County
Onshore wind
134 MWIn study Mclean, ILPJM Mar 2023target 2027
Solar project J2809, Iroquois County
Solar
133 MWIn study Iroquois, ILMISO Sep 2022target 2026
Nuclear project AH1-698, Will County
Nuclear · Constellation Energy Generation, LLC
130 MWIn study Will, ILPJM Apr 2025
Solar + storage project J2738, Rock Island County
Solar + storage
128 MWIn study Rock Island, ILMISO Sep 2022target 2025
Lincoln Capital Land LLC Solar Project
Solar · Lincoln Capital Land LLC
128 MWIn study Sangamon, ILMISO Aug 2025target 2028
Onshore wind project J3820, Hancock County
Onshore wind
127 MWIn study Hancock, ILMISO Apr 2024target 2028
Solar project J1679, Clay County
Solar
125 MWIn study Clay, ILMISO Jun 2020target 2026
Solar project J2384, Shelby County
Solar
125 MWIn study Shelby, ILMISO Sep 2022target 2024
Solar project AG2-516, Winnebago County
Solar · Kestrel Solar, LLC
120 MWIn study Winnebago, ILPJM Feb 2025target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)