OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 47

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 47 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project PIS069, Tooele County
Solar + storage · PacifiCorp
125 MWWithdrawn / abandoned Tooele, UTWest Jun 2024target 2028
Onshore wind project GI-0919, Bon Homme County
Onshore wind
125 MWWithdrawn / abandoned Bon Homme, SDWest Jul 2009target 2011
Solar project Q01, Pinal County
Solar
125 MWWithdrawn / abandoned Pinal, AZWest Jul 2008target 2014
Solar + storage project PIS067, Tooele County
Solar + storage · PacifiCorp
125 MWWithdrawn / abandoned Tooele, UTWest Jun 2024target 2028
Solar + storage project C4-070, Tooele County
Solar + storage · PacifiCorp
125 MWWithdrawn / abandoned Tooele, UTWest May 2024target 2028
Solar project PIS017, Emery County
Solar · PacifiCorp
125 MWWithdrawn / abandoned Emery, UTWest Jun 2022target 2025
Onshore wind project 2007-G10
Onshore wind
125 MWWithdrawn / abandoned West Dec 2007target 2011
Gas project 141, Elmore County
Gas
124 MWWithdrawn / abandoned Elmore, IDWest Jul 2005target 2007
Hydro project G0209, Grant County
Hydro
124 MWWithdrawn / abandoned Grant, WAWest Aug 2005target 2008
Gas project 139, Elmore County
Gas
124 MWWithdrawn / abandoned Elmore, IDWest Jul 2005target 2007
Onshore wind project TCS-02, Adams County
Onshore wind
123 MWWithdrawn / abandoned Adams, WAWest Jun 2018target 2021
Onshore wind project 62, Adams County
Onshore wind
123 MWWithdrawn / abandoned Adams, WAWest Jun 2018target 2021
Onshore wind project 305-A, Carbon County
Onshore wind
122 MWWithdrawn / abandoned Carbon, WYWest Nov 2009target 2012
Onshore wind project 305-B, Carbon County
Onshore wind
122 MWWithdrawn / abandoned Carbon, WYWest Nov 2009target 2012
Onshore wind project 305-C, Carbon County
Onshore wind
122 MWWithdrawn / abandoned Carbon, WYWest Nov 2009target 2013
Onshore wind project 23, Spokane County
Onshore wind
121 MWWithdrawn / abandoned Spokane, WAWest Oct 2009target 2012
Solar project IA-PNM-2017-22, Mckinley County
Solar
120 MWWithdrawn / abandoned Mckinley, NMWest Oct 2017target 2022
Solar project G0534, Wasco County
Solar
120 MWWithdrawn / abandoned Wasco, ORWest Apr 2016target 2019
Battery storage project Q93, Maricopa County
Battery storage
120 MWWithdrawn / abandoned Maricopa, AZWest Apr 2022target 2025
Onshore wind project GI-1308, Ward County
Onshore wind
120 MWWithdrawn / abandoned Ward, NDWest Jul 2013target 2015
Solar + storage project 1134, Klamath County
Solar + storage
120 MWWithdrawn / abandoned Klamath, ORWest May 2019target 2022
Solar + storage project IA-PNM-2019-02, Bernalillo County
Solar + storage
120 MWWithdrawn / abandoned Bernalillo, NMWest Apr 2019target 2020
Battery storage project G0720, Powell County
Battery storage
120 MWWithdrawn / abandoned Powell, MTWest Dec 2021target 2024
Onshore wind project GI-0929, Meade County
Onshore wind
120 MWWithdrawn / abandoned Meade, SDWest Oct 2009target 2011
Gas project BHCT-G2, Pueblo County
Gas · Black Hills Electric Generation LLC
120 MWWithdrawn / abandoned Pueblo, COWest Apr 2009target 2011
Solar + storage project 397, Silver Bow County
Solar + storage
120 MWWithdrawn / abandoned Silver Bow, MTWest Sep 2020target 2023
Onshore wind project Q107, Yavapai County
Onshore wind
120 MWWithdrawn / abandoned Yavapai, AZWest Mar 2010target 2012
Gas project 22-06281, Larimer County
Gas
120 MWWithdrawn / abandoned Larimer, COWest Jun 2022target 2027
Gas project 103, Cascade County
Gas
120 MWWithdrawn / abandoned Cascade, MTWest Feb 2009target 2011
Solar project 1130, Iron County
Solar
120 MWWithdrawn / abandoned Iron, UTWest Apr 2019target 2022
Onshore wind project GI-1302, Roosevelt County
Onshore wind
120 MWWithdrawn / abandoned Roosevelt, MTWest Mar 2013target 2016
Solar + storage project Company IK, Humboldt County
Solar + storage
120 MWWithdrawn / abandoned Humboldt, NVWest Mar 2018target 2020
Onshore wind project CS25-01, Spokane County
Onshore wind
120 MWWithdrawn / abandoned Spokane, WAWest Apr 2025target 2028
Onshore wind project CS23-03, Spokane County
Onshore wind
120 MWWithdrawn / abandoned Spokane, WAWest Apr 2023target 2027
Onshore wind project C4-044, Douglas County
Onshore wind
120 MWWithdrawn / abandoned Douglas, ORWest May 2024target 2029
Solar + storage project G0984, Deschutes County
Solar + storage
120 MWWithdrawn / abandoned Deschutes, ORWest Nov 2023target 2028
Battery storage project 668, Elmore County
Battery storage
120 MWWithdrawn / abandoned Elmore, IDWest Aug 2022
Oregon Energy Company
Gas · Oregon Energy Company LLC
120 MWWithdrawn / abandoned Linn, ORWest Sep 2000target 2001
Gas project G0352, Coos County
Gas
120 MWWithdrawn / abandoned Coos, ORWest Jan 2009target 2013
Libby 6th Unit
Hydro
120 MWWithdrawn / abandoned Lincoln, MTWest Mar 2008target 2010
Onshore wind project 2008-G13
Onshore wind
120 MWWithdrawn / abandoned West Sep 2008target 2011
Gas project GI-0617, Crawford County
Gas
120 MWWithdrawn / abandoned Crawford, IAWest Dec 2006
Solar project 1139, Klamath County
Solar
120 MWWithdrawn / abandoned Klamath, ORWest May 2019target 2022
Solar + storage project C3-061, San Juan County
Solar + storage
120 MWWithdrawn / abandoned San Juan, UTWest May 2023target 2026
Onshore wind project 2007-G3
Onshore wind
120 MWWithdrawn / abandoned West Jul 2007target 2010
Onshore wind project TCS-11, Spokane County
Onshore wind
120 MWWithdrawn / abandoned Spokane, WAWest Mar 2020target 2023
Gas project GI-0820, Brown County
Gas
120 MWWithdrawn / abandoned Brown, SDWest Jul 2008target 2011
Onshore wind project C3-188, Douglas County
Onshore wind
120 MWWithdrawn / abandoned Douglas, ORWest May 2023target 2028
Solar project G0550, Umatilla County
Solar
120 MWWithdrawn / abandoned Umatilla, ORWest Jul 2016target 2020
Onshore wind project 15, Idaho County
Onshore wind
120 MWWithdrawn / abandoned Idaho, IDWest Jun 2008target 2017
Page 47 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)