ONSHORE WIND Β· WEST

Onshore wind project 2008-G13

Onshore wind project 2008-G13 is a 120 MW onshore wind request withdrawn in the West interconnection queue, connecting to WAPA Rocky Mountain Region.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2008-G13
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Rocky Mountain Region
Connection point (POI)
Archer-Sidney 115-kV
Technology
Wind: 120 MW
Total requested
120 MW
Study phase
Withdrawn and Resubmitted
Queue status
Withdrawn
Entered queue
16 September 2008
Proposed online date
September 2011

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem