ONSHORE WIND Β· WEST

Onshore wind project C4-044, Douglas County

Onshore wind project C4-044, Douglas County is a 120 MW onshore wind request withdrawn in the West interconnection queue, in Douglas County, Oregon, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C4-044
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Dixonville substation
Location
Douglas County, Oregon
Technology
Wind: 120 MW
Total requested
120 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 May 2024
Proposed online date
December 2029

Location

Marker shows the centre of Douglas County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Douglas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem