ONSHORE WIND Β· WEST

Onshore wind project CS23-03, Spokane County

Onshore wind project CS23-03, Spokane County is a 120 MW onshore wind request withdrawn in the West interconnection queue, in Spokane County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
CS23-03
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Benewah 230kV Station
Location
Spokane County, Washington
Technology
Wind: 120 MW
Total requested
120 MW
Service type
NRIS and ERIS
Study phase
Request Status: Withdrawn; Phase One Cluster Study: Complete; Phase One Re-Study: N/A; Phase Two Cluster Study: Complete
Queue status
Withdrawn
Entered queue
18 April 2023
Proposed online date
December 2027
Withdrawn
December 2023

Location

Marker shows the centre of Spokane County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Spokane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem