United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 46

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 46 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2086, Barnes County
Solar
500 MWWithdrawn / abandoned Barnes, NDMISO Aug 2021target 2025
Other project G110, Bowman County
Other
500 MWWithdrawn / abandoned Bowman, NDMISO Jul 2001target 2006
Battery storage project C2-17, Converse County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Converse, WYWest Apr 2022target 2028
Mesa Solar
Solar
500 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2018
Coal project GI-0217, Stark County
Coal
500 MWWithdrawn / abandoned Stark, NDWest Nov 2002
Gila Solar
Solar
500 MWWithdrawn / abandoned Riverside, CACAISO Jul 2010target 2015
Onshore wind project GEN-2023-237, Hale County
Onshore wind
500 MWWithdrawn / abandoned Hale, TXSPP Oct 2023target 2030
Hereford Wind
Onshore wind · Higher Power Energy, LLC
500 MWWithdrawn / abandoned ERCOT Feb 2009target 2050
Genesee Wind Farm
Onshore wind · UPC Wind Management, LLC
500 MWWithdrawn / abandoned Genesee, NYNYISO Jan 2005
Battery storage project C3-069, Lake County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Lake, ORWest May 2023target 2030
Gas project B32, Dauphin County
Gas
500 MWWithdrawn / abandoned Dauphin, PAPJM Nov 1999
Oribi
Battery storage
500 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Onshore wind project J439, Emmet County
Onshore wind
500 MWWithdrawn / abandoned Emmet, IAMISO Mar 2015target 2016
Other project W3-065
Other
500 MWWithdrawn / abandoned PJM Sep 2010
Monte Cristo Solar 4
Solar
500 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Solar project J3626, Craighead County
Solar
500 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2027
Monte Cristo Solar 3
Solar
500 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Solar + storage project Company 239, Nye County
Solar + storage
500 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Greenpoint Energy Park
Other · GTM Energy, LLC
500 MWWithdrawn / abandoned NYNYISO Apr 2000
Gas project A14, Middlesex County
Gas
500 MWWithdrawn / abandoned Middlesex, NJPJM Jan 1998
Gas project G30_W55
Gas
500 MWWithdrawn / abandoned MDPJM May 2001target 2006
Onshore wind project GI-2021-20, Pueblo County
Onshore wind
500 MWWithdrawn / abandoned Pueblo, COWest Sep 2021target 2025
Battery storage project C3-068, Lincoln County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Lincoln, WYWest May 2023target 2030
Other project J1489, Ralls County
Other
500 MWWithdrawn / abandoned Ralls, MOMISO Apr 2019target 2024
Battery storage project C3-063, Carbon County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Carbon, UTWest May 2023target 2030
Solar + storage project Q430, Coconino County
Solar + storage
500 MWWithdrawn / abandoned Coconino, AZWest Sep 2021target 2024
Battery storage project AH1-754, Muskingum County
Battery storage · Cardinal Energy Storage East, LLC
500 MWWithdrawn / abandoned Muskingum, OHPJM target 2029
Battery storage project C3-046, Juab County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Juab, UTWest May 2023target 2030
Coal project GI-0319, Clay County
Coal
500 MWWithdrawn / abandoned Clay, SDWest Aug 2003
Solar + storage project Company QR, Washoe County
Solar + storage
500 MWWithdrawn / abandoned Washoe, NVWest Mar 2024target 2028
Battery storage project Company OO, Esmeralda County
Battery storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
Solar + storage project 158, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest Aug 2023target 2030
Battery storage project C2-18, Klamath County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Klamath, ORWest Apr 2022target 2028
Gas project G06_W45, Harrison County
Gas
500 MWWithdrawn / abandoned Harrison, WVPJM Feb 2001target 2005
Solar project J3426, Chicot County
Solar
500 MWWithdrawn / abandoned Chicot, ARMISO Mar 2024target 2028
Solar + storage project Company OQ, Lander County
Solar + storage
500 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2035
Chinook Energy Storage Center
Battery storage · Hydrostor USA Holdings, Inc , a subsidiary of Hydrostor Inc
500 MWWithdrawn / abandoned Lewis, NYNYISO Dec 2023
Onshore wind project AE1-197, White County
Onshore wind
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2021
Onshore wind project H082, Oliver County
Onshore wind
500 MWWithdrawn / abandoned Oliver, NDMISO Jun 2008target 2010
Cortes
Battery storage
500 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2018target 2021
Battery storage project C3-067, Grant County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Grant, WAWest May 2023target 2030
Battery storage project C2-26, Lake County
Battery storage · PacifiCorp
500 MWWithdrawn / abandoned Lake, ORWest Apr 2022target 2028
Onshore wind project U2-058, Christian County
Onshore wind
500 MWWithdrawn / abandoned Christian, ILPJM Jun 2008target 2011
Solar + storage project 694, Canyon County
Solar + storage
500 MWWithdrawn / abandoned Canyon, IDWest Dec 2022
Gas project 26, Pinellas County
Gas · Masked
500 MWWithdrawn / abandoned Pinellas, FLSoutheast Sep 2005target 2009
Solar + storage project Company 259, Nye County
Solar + storage
500 MWWithdrawn / abandoned Nye, NVWest Sep 2023target 2027
Onshore wind project 136, Converse County
Onshore wind · Clipper Windpower Development Company, Inc
500 MWWithdrawn / abandoned Converse, WYWest May 2007target 2012
Battery storage project 153, Pima County
Battery storage
500 MWWithdrawn / abandoned Pima, AZWest Mar 2023target 2028
Solar project AG2-655, Grant County
Solar · Mount Storm Solar, LLC
500 MWWithdrawn / abandoned Grant, WVPJM Mar 2021target 2024
Onshore wind project 872, Carbon County
Onshore wind
500 MWWithdrawn / abandoned Carbon, WYWest May 2017target 2020
Page 46 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)