πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Arizona

SOLAR + STORAGE Β· WEST

Solar + storage project 158, Pinal County

Solar + storage project 158, Pinal County is a 500 MW solar + storage request withdrawn in the West interconnection queue, in Pinal County, Arizona, connecting to Tucson Electric Power Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
158
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tucson Electric Power Company
Connection point (POI)
Pinal Central-Tortolita 500kV Transmission Line
Location
Pinal County, Arizona
Technology
Solar: 500 MW Β· Battery
Total requested
500 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
25 August 2023
Proposed online date
December 2030

Location

Marker shows the centre of Pinal County; the queue data does not give exact sites.

Power plants in Arizona Β· Transmission lines in Arizona

Other requests in Pinal County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem