United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESProjects with signed interconnection agreements in the USA — page 43
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Wind + storage project R101, Red Lake County Wind + storage |
4.6 MW | Agreement signed |
| Berkshire Wind Increase Onshore wind |
4.6 MW | Agreement signed |
| Hydro project GI-2020-18, Mesa County Hydro |
4.5 MW | Agreement signed |
| Lassen Lodge Hydroelectric Hydro |
4.5 MW | Agreement signed |
| Solar project 752, Malheur County Solar · Fry Foods Inc. |
4.2 MW | Agreement signed |
| Solar project GI-2009-7, Alamosa County Solar |
4.0 MW | Agreement signed |
| Cedar Lane Solar Solar |
4.0 MW | Agreement signed |
| RHC Solar Solar + storage |
3.9 MW | Agreement signed |
| Solar + storage project IC-1199, Lowndes County Solar + storage |
3.5 MW | Agreement signed |
| Rio Nogales CT1 Rotor Replacement Gas · CPS Energy |
3.1 MW | Agreement signed |
| CPS Rio Nogales CT301 Rotor Replacement Gas · CPS Energy |
3.1 MW | Agreement signed |
| CPS Rio Nogales CT201 Rotor Replacement Gas · CPS Energy |
3.1 MW | Agreement signed |
| Sweetwater 1 repower Onshore wind · Leeward Energy |
3.0 MW | Agreement signed |
| GGC Solar Solar + storage |
2.7 MW | Agreement signed |
| Battery storage project C1-15, Klamath County Battery storage · PacifiCorp |
2.3 MW | Agreement signed |
| Solar project 11 Solar |
2.0 MW | Agreement signed |
| Roxbury Solar Solar |
2.0 MW | Agreement signed |
| Other project J953, Johnson County Other |
2.0 MW | Agreement signed |
| Solar project CS24-07, Adams County Solar |
2.0 MW | Agreement signed |
| Hydro project 899609, Jackson County Hydro |
1.8 MW | Agreement signed |
| Monroe-Sicklerville Road LF Solar Solar |
1.6 MW | Agreement signed |
| Hydro project 899793, Jackson County Hydro |
1.5 MW | Agreement signed |
| NEA Bell. Uprate (Northeast Energy Associates, LP) Gas |
1.4 MW | Agreement signed |
| Solar project J954, Johnson County Solar |
1.4 MW | Agreement signed |
| Other project Company MN, Lyon County Other |
1.3 MW | Agreement signed |
| Solar project CS24-01, Adams County Solar |
1.0 MW | Agreement signed |
| Onshore wind project G081, Pipestone County Onshore wind |
1.0 MW | Agreement signed |
| Other project J258, Stearns County Other |
1.0 MW | Agreement signed |
| Hydro project 1186, Bannock County Hydro · Commercial Energy Management, Inc. |
0.9 MW | Agreement signed |
| Gas project GI-1103, Burke County Gas · Blaise Energy |
0.8 MW | Agreement signed |
| Solar project TCS-40, Benton County Solar · Oregon State University |
0.8 MW | Agreement signed |
| Lassen Lodge Hydroelectric 2 Hydro |
0.5 MW | Agreement signed |
| Battery storage project CS24-02, Spokane County Battery storage |
0.5 MW | Agreement signed |
| Hydro project 973, Franklin County Hydro · City of Preston |
0.4 MW | Agreement signed |
| Champion Wind Repower Onshore wind · Champion Wind Farm, LLC |
0.3 MW | Agreement signed |
| Solar project TCS-38, Benton County Solar · Oregon State University |
0.3 MW | Agreement signed |
| Solar project TCS-39, Benton County Solar · Oregon State University |
0.2 MW | Agreement signed |
| Hydro project 755, Gem County Hydro · Emmett Main Canal |
0.1 MW | Agreement signed |
| Silver Star repower Onshore wind · Silver Star I Power Partners, LLC |
-7.2 MW | Agreement signed |
| Sherbino II Wind repower Onshore wind · Sherbino II Wind Farm LLC |
-18.0 MW | Agreement signed |
| Trinity Hills Wind repower Onshore wind · Trinity Hills Wind Farm LLC |
-27.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)578 · 119.3 GW
- CAISO (California)235 · 96.2 GW
- West (non-ISO utilities)349 · 60.6 GW
- Southeast (non-ISO utilities)192 · 37.8 GW
- SPP (Southwest Power Pool)212 · 37.6 GW
- PJM (Mid-Atlantic, Midwest)343 · 35.0 GW
- MISO (Midcontinent)187 · 28.1 GW
- ISO-NE (New England)45 · 8,609 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)