United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 422

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 422 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-210, Fayette County
Solar
12.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Solar project Q189, Maricopa County
Solar
12.0 MWWithdrawn / abandoned Maricopa, AZWest Feb 2011target 2013
Onshore wind project J768, Story County
Onshore wind
12.0 MWWithdrawn / abandoned Story, IAMISO Nov 2016target 2019
Onshore wind project G328, Mchenry County
Onshore wind
12.0 MWWithdrawn / abandoned Mchenry, NDMISO Apr 2003target 2003
Solar project AH1-200, Wyoming County
Solar
12.0 MWWithdrawn / abandoned Wyoming, PAPJM Sep 2021target 2023
Solar project AH1-211, Fayette County
Solar
12.0 MWWithdrawn / abandoned Fayette, PAPJM Sep 2021target 2024
Gas project Q35, Maricopa County
Gas
12.0 MWWithdrawn / abandoned Maricopa, AZWest Jul 2014target 2014
Solar project W3-055, Burlington County
Solar
12.0 MWWithdrawn / abandoned Burlington, NJPJM Sep 2010target 2011
Other project G151, Mcintosh County
Other
12.0 MWWithdrawn / abandoned Mcintosh, NDMISO Nov 2001target 2002
Solar project AH1-068, Gloucester County
Solar
12.0 MWWithdrawn / abandoned Gloucester, NJPJM Jul 2021target 2023
Emsworth Back Channel Dam Hydroelectric Project
Hydro
12.0 MWWithdrawn / abandoned Allegheny, PAPJM Mar 2020target 2024
Solar project IC-529, Pickens County
Solar
12.0 MWWithdrawn / abandoned Pickens, ALSoutheast Nov 2016
Onshore wind project MPC03100, Cass County
Onshore wind
11.9 MWWithdrawn / abandoned Cass, NDMISO Nov 2016target 2018
Solar project X3-074, Kent County
Solar
11.9 MWWithdrawn / abandoned Kent, MDPJM Oct 2011target 2013
Battery Storage
Battery storage
11.9 MWWithdrawn / abandoned Franklin, MAISO-NE Sep 2022target 2027
Fayetteville Solar
Solar
11.9 MWWithdrawn / abandoned Franklin, PAPJM Sep 2019target 2022
Wind
Onshore wind
11.9 MWWithdrawn / abandoned Lincoln, MEISO-NE Nov 2011target 2017
Eversource Group @ Sandwich 916
Solar + storage
11.8 MWWithdrawn / abandoned Barnstable, MAISO-NE Apr 2020target 2023
Other project 121, Osceola County
Other · Masked
11.8 MWWithdrawn / abandoned Osceola, FLSoutheast Jul 2013target 2014
Solar
Solar
11.8 MWWithdrawn / abandoned Washington, MEISO-NE Sep 2020target 2023
Des
Solar
11.8 MWWithdrawn / abandoned Fresno, CACAISO Aug 2010target 2013
Other project 404, Sanpete County
Other
11.8 MWWithdrawn / abandoned Sanpete, UTWest Nov 2011target 2013
Solar and Battery
Solar + storage
11.7 MWWithdrawn / abandoned York, MEISO-NE Aug 2019target 2020
Millbury Substation - NG WMA Group 3
Solar + storage
11.7 MWWithdrawn / abandoned Worcester, MAISO-NE Oct 2021target 2027
Other project 128, Suwannee County
Other · Duke Energy Florida, LLC
11.7 MWWithdrawn / abandoned Suwannee, FLSoutheast Dec 2013target 2015
Offshore Wind
Offshore wind
11.6 MWWithdrawn / abandoned MEISO-NE Jul 2021target 2023
Fresh Kills Battery Storage
Battery storage · Consolidated Edison
11.6 MWWithdrawn / abandoned NYNYISO Sep 2023
The Bruckner
Battery storage · 174 Power Global Properties, LLC
11.6 MWWithdrawn / abandoned Bronx, NYNYISO Sep 2021
Onshore wind project G496, Goodhue County
Onshore wind
11.6 MWWithdrawn / abandoned Goodhue, MNMISO Feb 2005
Newcastle 115 kV SS - Midcoast Area DG Study
Solar
11.6 MWWithdrawn / abandoned Cumberland, MEISO-NE Oct 2023target 2024
Other project AC2-189, Somerset County
Other
11.6 MWWithdrawn / abandoned Somerset, MDPJM Mar 2017target 2018
Onshore wind project 359, Lincoln County
Onshore wind
11.5 MWWithdrawn / abandoned Lincoln, IDWest Nov 2010
Hydro project 617, Utah County
Hydro
11.5 MWWithdrawn / abandoned Utah, UTWest Sep 2014target 2017
Hydro project 656, Utah County
Hydro
11.5 MWWithdrawn / abandoned Utah, UTWest Apr 2015target 2018
Solar project GEN-2022-084, Jasper County
Solar
11.5 MWWithdrawn / abandoned Jasper, MOSPP Oct 2022target 2026
Hydro project 645, Utah County
Hydro
11.5 MWWithdrawn / abandoned Utah, UTWest Feb 2015target 2017
Solar project AH1-182, Pulaski County
Solar
11.5 MWWithdrawn / abandoned Pulaski, VAPJM Aug 2021target 2022
Replace 11.4 of WPS.LAKEFRN96 Unit with natural gas (with diesel as a backup); Lakefront 9
Gas
11.4 MWWithdrawn / abandoned Manitowoc, WIMISO Jul 2020target 2022
Mount Lassen Power Plant
Other
11.4 MWWithdrawn / abandoned Lassen, CACAISO Apr 2023target 2028
Other project U2-085, Lancaster County
Other
11.4 MWWithdrawn / abandoned Lancaster, PAPJM Jul 2008target 2009
Livonia BESS
Battery storage · Dimension NY 1 LLC
11.3 MWWithdrawn / abandoned Livingston, NYNYISO Nov 2019
Westwood Rd
Solar · Solar Liberty Energy Systems, Inc.
11.3 MWWithdrawn / abandoned Erie, NYNYISO Sep 2017
Solar project AG2-340, Halifax County
Solar
11.3 MWWithdrawn / abandoned Halifax, VAPJM Mar 2021target 2024
Eversource Group Study @ Industrial Park
Solar + storage
11.3 MWWithdrawn / abandoned Bristol, MAISO-NE Mar 2020target 2023
Solar project AG2-228, Warren County
Solar · Reeder Farm Solar Farm, LLC
11.2 MWWithdrawn / abandoned Warren, NJPJM Mar 2021target 2022
Other project 132, Osceola County
Other · Masked
11.2 MWWithdrawn / abandoned Osceola, FLSoutheast Apr 2014target 2015
Solar project X2-002, Somerset County
Solar
11.2 MWWithdrawn / abandoned Somerset, NJPJM May 2011target 2012
Repowered Mckittrick Cogen Plant
Gas
11.2 MWWithdrawn / abandoned Kern, CACAISO Jul 2010target 2011
Oak Grove III
Solar
11.2 MWWithdrawn / abandoned Westmoreland, VAPJM Jul 2017target 2021
Solar project X1-105, Sussex County
Solar
11.2 MWWithdrawn / abandoned Sussex, NJPJM Apr 2011target 2012
Page 422 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)