Solar project AH1-182, Pulaski County

Solar project AH1-182, Pulaski County is a 11.5 MW solar request withdrawn in the PJM interconnection queue, in Pulaski County, Virginia, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-182
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Peak Creek 34.5
Location
Pulaski County, Virginia
Technology
Solar: 11.5 MW
Total requested
11.5 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 August 2021
Proposed online date
December 2022
Withdrawn
December 2024

Location

Marker shows the centre of Pulaski County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in Pulaski County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem