BATTERY STORAGE Β· NYISOFresh Kills Battery Storage
Fresh Kills Battery Storage is a 11.6 MW battery storage request withdrawn in the NYISO interconnection queue, connecting to ConEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2023 (completed)
- Withdrawn / abandonedSep 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1608
- Grid region
- NYISO (New York)
- Utility / transmission owner
- ConEd
- Developer
- Consolidated Edison
- Connection point (POI)
- Fresh Kills Substation
- Location
- New York
- Technology
- Battery: 11.6 MW
- Total requested
- 11.6 MW
- Queue status
- Withdrawn
- Entered queue
- 20 September 2023
- Withdrawn
- September 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem