🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 42

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 42 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AC1-022, Brown County
Solar
60.0 MWWithdrawn / abandoned Brown, OHPJM Jul 2016target 2017
Solar project AH1-649, Greensville County
Solar
60.0 MWWithdrawn / abandoned Greensville, VAPJM Sep 2021target 2024
Onshore wind project R06, Carbon County
Onshore wind
60.0 MWWithdrawn / abandoned Carbon, PAPJM Sep 2006target 2008
Solar + storage project AG2-032, Salem County
Solar + storage
60.0 MWWithdrawn / abandoned Salem, NJPJM Oct 2020target 2023
Battery storage project AF2-393, Adams County
Battery storage · Bison Meadows Wind Project, LLC
60.0 MWWithdrawn / abandoned Adams, ILPJM Mar 2020target 2024
Warwick PVI
Solar
60.0 MWWithdrawn / abandoned Prince George, VAPJM Feb 2017target 2022
Solar project AH1-081, Metcalfe County
Solar · Wildrye Solar LLC
60.0 MWWithdrawn / abandoned Metcalfe, KYPJM Jul 2021target 2024
Onshore wind project X1-019, Dauphin County
Onshore wind
60.0 MWWithdrawn / abandoned Dauphin, PAPJM Feb 2011target 2013
Solar project AE2-235, Mason County
Solar
60.0 MWWithdrawn / abandoned Mason, KYPJM Mar 2019target 2021
Solar project AD2-036, Harrison County
Solar
60.0 MWWithdrawn / abandoned Harrison, KYPJM Jan 2018target 2020
Solar project AH1-052, Mecklenburg County
Solar
60.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Jul 2021target 2025
Solar project AC1-156, Pulaski County
Solar
60.0 MWWithdrawn / abandoned Pulaski, VAPJM Oct 2016target 2019
Caden Energix Spout Spring
Solar
60.0 MWWithdrawn / abandoned Appomattox, VAPJM Jul 2018target 2025
Gas project X4-007, Charles County
Gas
60.0 MWWithdrawn / abandoned Charles, MDPJM Nov 2011target 2015
Onshore wind project Q72, Bradford County
Onshore wind
60.0 MWWithdrawn / abandoned Bradford, PAPJM Jul 2006target 2010
Onshore wind project P39, Stark County
Onshore wind
60.0 MWWithdrawn / abandoned Stark, ILPJM Dec 2005target 2008
Solar + storage project AG2-179, Adair County
Solar + storage · Round Trip, LLC
60.0 MWWithdrawn / abandoned Adair, KYPJM Mar 2025target 2023
Solar project AF1-308, Pike County
Solar
60.0 MWWithdrawn / abandoned Pike, OHPJM Sep 2019target 2023
Battery storage project AH1-447, Pittsylvania County
Battery storage · Cascade Energy Storage, LLC
60.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Sep 2021target 2024
Solar project AE2-186, Fauquier County
Solar
60.0 MWWithdrawn / abandoned Fauquier, VAPJM Mar 2019target 2020
Shockoe Solar Farm
Solar · Zenith Solar, LLC
60.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Mar 2019target 2020
Elkwood Solar
Solar
60.0 MWWithdrawn / abandoned Culpeper, VAPJM Oct 2016target 2023
Solar project AH1-375, Fluvanna County
Solar
60.0 MWWithdrawn / abandoned Fluvanna, VAPJM Sep 2021target 2025
Onshore wind project L04, Westmoreland County
Onshore wind
60.0 MWWithdrawn / abandoned Westmoreland, PAPJM Oct 2003target 2005
Shawboro East Ridge Solar Park
Solar
60.0 MWWithdrawn / abandoned Currituck, NCPJM Oct 2014target 2015
Solar project AG2-507, Nottoway County
Solar
60.0 MWWithdrawn / abandoned Nottoway, VAPJM Mar 2021target 2025
Other project AA1-035
Other
60.0 MWWithdrawn / abandoned PJM Aug 2014
6011 Greenwich Windpark, LLC
Onshore wind
60.0 MWWithdrawn / abandoned Huron, OHPJM Aug 2011target 2017
Battery storage project AH1-318, Franklin County
Battery storage · Invenergy Storage Development LLC
60.0 MWWithdrawn / abandoned Franklin, OHPJM Sep 2021target 2025
Onshore wind project O71, Somerset County
Onshore wind
60.0 MWWithdrawn / abandoned Somerset, PAPJM Jul 2005target 2007
Solar project AB1-134, Queen Anne's County
Solar
60.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2015target 2016
Solar project AG1-043, Accomack County
Solar
60.0 MWWithdrawn / abandoned Accomack, VAPJM Jun 2020target 2023
Battery storage project AF1-107, Warren County
Battery storage
60.0 MWWithdrawn / abandoned Warren, NJPJM Sep 2019target 2023
Solar + storage project AH1-093, Halifax County
Solar + storage
60.0 MWWithdrawn / abandoned Halifax, VAPJM Jul 2021target 2025
North Briery WF
Onshore wind
60.0 MWWithdrawn / abandoned Preston, WVPJM Jan 2005target 2012
Battery storage project AH1-432, Randolph County
Battery storage · ACE Development Company, LLC
60.0 MWWithdrawn / abandoned Randolph, INPJM Sep 2021target 2025
Battery storage project AJ1-009, Essex County
Battery storage
60.0 MWWithdrawn / abandoned Essex, NJPJM May 2023target 2027
Solar + storage project AH2-277, Buchanan County
Solar + storage
60.0 MWWithdrawn / abandoned Buchanan, VAPJM Mar 2022target 2024
Onshore wind project U2-051, Giles County
Onshore wind
60.0 MWWithdrawn / abandoned Giles, VAPJM Jun 2008target 2010
Solar project AF2-176, Mercer County
Solar · Sanderson Solar LLC
60.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2020target 2022
Solar project AH1-250, Spotsylvania County
Solar
60.0 MWWithdrawn / abandoned Spotsylvania, VAPJM Sep 2021target 2024
Solar + storage project AG1-078, Garrett County
Solar + storage
60.0 MWWithdrawn / abandoned Garrett, MDPJM Jul 2020target 2023
Solar project AH2-222
Solar
60.0 MWWithdrawn / abandoned KYPJM Mar 2022target 2026
Solar project AF1-271, Butler County
Solar
60.0 MWWithdrawn / abandoned Butler, PAPJM Sep 2019target 2023
Solar project AF2-049, Caroline County
Solar
60.0 MWWithdrawn / abandoned Caroline, VAPJM Dec 2019target 2021
Solar project AG2-008, Erie County
Solar · Blatche Solar, LLC
60.0 MWWithdrawn / abandoned Erie, PAPJM Oct 2020target 2023
Onshore wind project R53, Lackawanna County
Onshore wind
60.0 MWWithdrawn / abandoned Lackawanna, PAPJM Dec 2006target 2009
Solar + storage project AG1-544, Prince George County
Solar + storage
60.0 MWWithdrawn / abandoned Prince George, VAPJM Sep 2020target 2024
Solar project AF2-381, Somerset County
Solar · Panther Run Solar, LLC
60.0 MWWithdrawn / abandoned Somerset, PAPJM Apr 2020target 2023
Solar project AC2-048, Meigs County
Solar
60.0 MWWithdrawn / abandoned Meigs, OHPJM Feb 2017target 2018
Page 42 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)