๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2023 requests) โ€” page 41

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,063551.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,063 requests ยท page 41 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Other project C3-145, Bonneville County
Other
5.4 MWWithdrawn / abandoned Bonneville, IDWest May 2023target 2025
Scitico DG Cluster
Solar + storage
5.2 MWWithdrawn / abandoned Hartford, CTISO-NE Jan 2023target 2023
Battery Storage
Battery storage
5.1 MWWithdrawn / abandoned Middlesex, CTISO-NE Jan 2023target 2025
NG NEMA Group DER Study
Solar + storage
5.0 MWWithdrawn / abandoned Essex, MAISO-NE Dec 2023target 2025
Leeds 115 kV SS - Sturtevant-Leeds-Livermore-Ludden-Riley Area DG Study
Solar
5.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Sep 2023target 2024
Solar project 898329, Florence County
Solar
5.0 MWWithdrawn / abandoned Florence, SCSoutheast Jun 2023
Other project C3-151, Millard County
Other
5.0 MWWithdrawn / abandoned Millard, UTWest May 2023target 2026
Solar project C3-071, Box Elder County
Solar
5.0 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2024
CMP Spring St 115 kV SS - Greater Portland Area DG Study
Solar
5.0 MWWithdrawn / abandoned Cumberland, MEISO-NE Dec 2023target 2024
Individual @ Montague
Battery storage
5.0 MWWithdrawn / abandoned Franklin, MAISO-NE Jun 2023target 2024
Solar + storage project C3-089, Washington County
Solar + storage ยท PacifiCorp
5.0 MWWithdrawn / abandoned Washington, UTWest May 2023target 2028
NG NEMA Group DER Study
Battery storage
5.0 MWWithdrawn / abandoned Middlesex, MAISO-NE Dec 2023target 2025
Sturtevant 115 kV SS - Sturtevant-Leeds-Livermore-Ludden-Riley Area Study
Solar
5.0 MWWithdrawn / abandoned Franklin, MEISO-NE Sep 2023target 2024
Solar + storage project C3-118, Duchesne County
Solar + storage
5.0 MWWithdrawn / abandoned Duchesne, UTWest May 2023target 2028
OATT NYISO Tuxedo Project
Battery storage ยท Radial Power LLC (Radial Power BESS NY LLC)
5.0 MWWithdrawn / abandoned Orange, NYNYISO Feb 2023
CMP Elm St 115 kV SS - Greater Portland Area DG Study
Solar
5.0 MWWithdrawn / abandoned Cumberland, MEISO-NE Dec 2023target 2024
CMP Biddeford IP 115 kV SS - Louden-Biddeford Area DG Study
Solar
4.9 MWWithdrawn / abandoned York, MEISO-NE Dec 2023target 2024
Lincolnville 115 kV SS - Midcoast Area DG Study
Solar
4.9 MWWithdrawn / abandoned Lincoln, MEISO-NE Oct 2023target 2024
CMP West Buxton 115 kV SS - Louden-Biddeford Area DG Study
Solar
4.5 MWWithdrawn / abandoned York, MEISO-NE Dec 2023target 2024
Battery storage project 898287, Randolph County
Battery storage
4.3 MWWithdrawn / abandoned Randolph, NCSoutheast Jun 2023target 2026
Onshore wind project C3-084, Converse County
Onshore wind ยท PacifiCorp
4.2 MWWithdrawn / abandoned Converse, WYWest May 2023target 2023
Individual @ Piper
Other
4.1 MWWithdrawn / abandoned Hampden, MAISO-NE Jun 2023target 2026
CMP Moshers/Prides Corner 115 kV SS - Greater Portland Area DG Study
Other
4.0 MWWithdrawn / abandoned Cumberland, MEISO-NE Dec 2023target 2024
Individual @ Partridge
Solar + storage
4.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Jun 2023target 2024
Group @ Orchard
Solar + storage
4.0 MWWithdrawn / abandoned Hampden, MAISO-NE Jun 2023target 2026
Mason 115 kV SS - Midcoast Area DG Study
Solar
3.9 MWWithdrawn / abandoned Lincoln, MEISO-NE Oct 2023target 2024
Bantam Energy Storage
Battery storage
3.8 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Pascal Energy Storage
Battery storage
3.7 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
San Ysidro Energy Storage
Battery storage
3.7 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Frates
Battery storage
3.7 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Coyote Ranch Energy Storage
Battery storage
3.7 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Onshore wind project C3-091, Albany County
Onshore wind ยท PacifiCorp
3.6 MWWithdrawn / abandoned Albany, WYWest May 2023target 2024
Hydro project 450, Lewis And Clark County
Hydro
3.4 MWWithdrawn / abandoned Lewis And Clark, MTWest Oct 2023target 2025
Bath 115 kV SS - Midcoast Area DG Study
Solar
3.4 MWWithdrawn / abandoned Lincoln, MEISO-NE Oct 2023target 2024
Solar project 442, Valley County
Solar
3.0 MWWithdrawn / abandoned Valley, MTWest Mar 2023target 2025
Solar project C3-177, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2024
Solar project C3-178, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest May 2023target 2024
Coopers Mills 115 kV SS - Midcoast Area DG Study
Solar
2.9 MWWithdrawn / abandoned Lincoln, MEISO-NE Oct 2023target 2024
Solar project C3-014, Klamath County
Solar
2.5 MWWithdrawn / abandoned Klamath, ORWest Apr 2023target 2024
Individual @ French King
Solar + storage
2.2 MWWithdrawn / abandoned Franklin, MAISO-NE Jun 2023
Solar project C3-070, Weber County
Solar
2.0 MWWithdrawn / abandoned Weber, UTWest May 2023target 2024
Cayuta Add-on
Battery storage ยท Nexamp
2.0 MWWithdrawn / abandoned Schuyler, NYNYISO Mar 2023
CMP Vallee Lane 115 kV SS - Louden-Biddeford Area DG Study
Solar
2.0 MWWithdrawn / abandoned Cumberland, MEISO-NE Dec 2023target 2024
Athens 115 kV SS - CMP Wyman Area Study
Solar
2.0 MWWithdrawn / abandoned Somerset, MEISO-NE Mar 2023target 2024
Ludden Lane 115 kV SS - Sturtevant-Leeds-Livermore-Ludden-Riley Area DG Study
Solar
2.0 MWWithdrawn / abandoned Oxford, MEISO-NE Sep 2023target 2024
Topsham 115 kV SS - Midcoast Area DG Study
Solar
2.0 MWWithdrawn / abandoned Waldo, MEISO-NE Oct 2023target 2024
Individual @ Amherst
Battery storage
2.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2023target 2024
Solar project C3-074, Millard County
Solar
2.0 MWWithdrawn / abandoned Millard, UTWest May 2023target 2023
Cayuta Add-on
Battery storage ยท Nexamp Solar
2.0 MWWithdrawn / abandoned Schuyler, NYNYISO Oct 2023
Highland/Park St 115 kV SS - Midcoast Area DG Study
Solar
2.0 MWWithdrawn / abandoned Knox, MEISO-NE Oct 2023target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)