United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

HYDRO Β· WEST

Hydro project 450, Lewis And Clark County

Hydro project 450, Lewis And Clark County is a 3.4 MW hydro request withdrawn in the West interconnection queue, in Lewis And Clark County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
450
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Hauser Dam Substation
Location
Lewis And Clark County, Montana
Technology
Hydro: 3.4 MW
Total requested
3.4 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
17 October 2023
Proposed online date
June 2025

Location

Marker shows the centre of Lewis And Clark County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Lewis And Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem