United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

OATT NYISO Tuxedo Project

OATT NYISO Tuxedo Project is a 5.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Orange County, New York, connecting to O&R.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1526
Grid region
NYISO (New York)
Utility / transmission owner
O&R
Developer
Radial Power LLC (Radial Power BESS NY LLC)
Connection point (POI)
55 NY 17, Tuxedo Park, NY 10987
Location
Orange County, New York
Technology
Battery: 5.0 MW
Total requested
5.0 MW
Queue status
Withdrawn
Entered queue
25 February 2023
Withdrawn
March 2023

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Orange County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem