United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2011 requests) โ page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Desert Bell Solar Solar |
200 MW | Withdrawn / abandoned |
| Gulf Wind 2 Onshore wind ยท Pattern Energy Group |
200 MW | Withdrawn / abandoned |
| Solar project Q178, San Juan County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2011-001, Smith County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G991, Fillmore County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2011-058, Lynn County Onshore wind |
200 MW | Withdrawn / abandoned |
| Mount Signal Solar Farm III Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project H025, Minnehaha County Onshore wind |
200 MW | Withdrawn / abandoned |
| Coal project X1-027, Scioto County Coal |
200 MW | Withdrawn / abandoned |
| Other project Company FK, White Pine County Other |
200 MW | Withdrawn / abandoned |
| Onshore wind project J094, Manitowoc County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J195, Shiawassee County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J205, Montgomery County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J222, Gratiot County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project X2-020, Erie County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J213, Sangamon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G771, Howard County Onshore wind |
200 MW | Withdrawn / abandoned |
| Silurian Valley Wind Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G961, Goodhue County Onshore wind |
200 MW | Withdrawn / abandoned |
| Daggett Solar Project Solar |
200 MW | Withdrawn / abandoned |
| Mojave View Solar Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J204, Calhoun County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project 145, Stillwater County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GI-1104, Pennington County Onshore wind |
200 MW | Withdrawn / abandoned |
| Gas project 229, Clay County Gas |
200 MW | Withdrawn / abandoned |
| Onshore wind project 147, Stillwater County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project G757, Adams County Onshore wind |
200 MW | Withdrawn / abandoned |
| Sun Valley Energy Center-1 Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project G960, Goodhue County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2011-006, Osage County Onshore wind |
200 MW | Withdrawn / abandoned |
| Wind Onshore wind |
198 MW | Withdrawn / abandoned |
| Gas project GEN-2011-031, Ector County Gas |
196 MW | Withdrawn / abandoned |
| Clover Leaf Hollers Ave Gas ยท Clover Leaf Power, LLC |
193 MW | Withdrawn / abandoned |
| Onshore wind project 398-A, Bonneville County Onshore wind |
192 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2011-032, Clark County Onshore wind |
180 MW | Withdrawn / abandoned |
| Onshore wind project 32, Kittitas County Onshore wind |
176 MW | Withdrawn / abandoned |
| Onshore wind project X2-021, Erie County Onshore wind |
154 MW | Withdrawn / abandoned |
| Onshore wind project J125, Macon County Onshore wind |
151 MW | Withdrawn / abandoned |
| Watkins Glen East Onshore wind ยท NextEra Energy Resources, LLC |
151 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2011-005, Butler County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2011-009, Washita County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2011-004, Cowley County Onshore wind |
150 MW | Withdrawn / abandoned |
| Tulare Solar Solar |
150 MW | Withdrawn / abandoned |
| Candlewood Wind Onshore wind |
150 MW | Withdrawn / abandoned |
| Great Bay Wind Farm Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project X3-031, Allen County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J214, Marshall County Onshore wind |
150 MW | Withdrawn / abandoned |
| Acorn Greenworks Solar |
150 MW | Withdrawn / abandoned |
| Solar project Company 110, Clark County Solar |
150 MW | Withdrawn / abandoned |
| Maricopa California Solar Farms II Solar |
150 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)187 ยท 30.0 GW
- PJM (Mid-Atlantic, Midwest)289 ยท 22.9 GW
- Southeast (non-ISO utilities)32 ยท 14.0 GW
- West (non-ISO utilities)157 ยท 12.8 GW
- MISO (Midcontinent)51 ยท 10.5 GW
- SPP (Southwest Power Pool)43 ยท 8,099 MW
- ERCOT (Texas)26 ยท 4,638 MW
- ISO-NE (New England)14 ยท 1,774 MW
- NYISO (New York)9 ยท 1,394 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)