ONSHORE WIND Β· SPP

Onshore wind project GEN-2011-058, Lynn County

Onshore wind project GEN-2011-058, Lynn County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Lynn County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2011 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2011-058
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap Grassland - Borden 230kV
Location
Lynn County, Texas
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 September 2011
Proposed online date
November 2012
Withdrawn
March 2012

Location

Marker shows the centre of Lynn County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Lynn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem