Queue requests in study in Virginia — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown21523.0 GW
Active in queue30.3 GW287 requests
Agreement signed7,318 MW72 requests
Withdrawn86886.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

215 requests · page 4 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AH2-268, Dinwiddie County
Solar + storage
37.0 MWIn study Dinwiddie, VAPJM Mar 2022target 2025
Solar + storage project AH2-404, Pittsylvania County
Solar + storage
35.0 MWIn study Pittsylvania, VAPJM Mar 2022target 2026
Solar + storage project AH2-151, Halifax County
Solar + storage
35.0 MWIn study Halifax, VAPJM Feb 2022target 2025
Solar + storage project AG2-426, Sussex County
Solar + storage · Waverly Solar 1, LLC
33.5 MWIn study Sussex, VAPJM Feb 2025target 2024
Battery storage project AJ1-038, York County
Battery storage
33.0 MWIn study York, VAPJM Jun 2023target 2025
Solar project AI2-153, Louisa County
Solar
32.0 MWIn study Louisa, VAPJM Mar 2023target 2022
Solar project AI2-145, Montgomery County
Solar
30.4 MWIn study Montgomery, VAPJM Feb 2023target 2022
Battery storage project AI2-278, Lancaster County
Battery storage
30.0 MWIn study Lancaster, VAPJM Mar 2023target 2027
Redbud-Gaylord 34.5 kV
Solar
30.0 MWPaused / redesign Frederick, VAPJM Jul 2020target 2026
Battery storage project AI2-227, Amherst County
Battery storage
30.0 MWIn study Amherst, VAPJM Mar 2023target 2023
Battery storage project AH2-059, Prince William County
Battery storage
30.0 MWIn study Prince William, VAPJM Dec 2021target 2027
Battery storage project AH2-058, Prince William County
Battery storage
30.0 MWIn study Prince William, VAPJM Dec 2021target 2026
Battery storage project AG2-566, Prince Edward County
Battery storage · Gabriel Storage, LLC
30.0 MWIn study Prince Edward, VAPJM Feb 2025target 2024
Solar project AH2-057, Buckingham County
Solar
29.9 MWIn study Buckingham, VAPJM Dec 2021target 2025
Solar project AI2-338, Charles City County
Solar
29.2 MWIn study Charles City, VAPJM Mar 2023target 2024
Battery storage project AH2-075, City Of Hampton County
Battery storage
29.1 MWIn study City Of Hampton, VAPJM Jan 2022target 2024
360 Solar Center, LLC
Solar · 360 Solar Center, LLC
26.0 MWIn study Chesterfield, VAPJM Feb 2025target 2023
360 Solar Center, LLC
Solar · 360 Solar Center, LLC
26.0 MWIn study Chesterfield, VAPJM Feb 2025target 2023
Amelia Energy Facility
Solar · Amelia Energy Facility, LLC
25.0 MWIn study Amelia, VAPJM Feb 2020target 2022
Battery storage project AH2-048, Northampton County
Battery storage
20.0 MWIn study Northampton, VAPJM Dec 2021target 2025
Amelia Energy Facility
Solar · Amelia Energy Facility, LLC
20.0 MWIn study Amelia, VAPJM May 2020target 2023
Reid Energy Center
Battery storage · Reid Energy Center, LLC
20.0 MWIn study Prince William, VAPJM Feb 2025target 2022
Evergreen Energy Center
Battery storage · Evergreen Energy Center, LLC
20.0 MWIn study Loudoun, VAPJM Feb 2025target 2022
Switchgrass Solar 1
Solar
20.0 MWPaused / redesign Accomack, VAPJM Feb 2020target 2025
Battery storage project AI2-010, Hanover County
Battery storage
20.0 MWIn study Hanover, VAPJM Nov 2022target 2025
Solar project AG2-193, Henrico County
Solar · Virginia Electric and Power Company
20.0 MWIn study Henrico, VAPJM Feb 2025target 2023
Battery storage project AH2-050, Accomack County
Battery storage
20.0 MWIn study Accomack, VAPJM Dec 2021target 2025
Solar project AH1-072, Dickenson County
Solar · Bold Camp CF Solar, LLC
20.0 MWIn study Dickenson, VAPJM Mar 2025target 2024
Solar project AI2-175, Westmoreland County
Solar
20.0 MWIn study Westmoreland, VAPJM Feb 2023target 2025
Horsepen Creek Solar I
Solar · Horsepen Creek Solar, LLC
20.0 MWIn study Goochland, VAPJM Mar 2025target 2024
Solar project AH1-280, Amelia County
Solar · Amelia Energy Facility, LLC
20.0 MWIn study Amelia, VAPJM Feb 2025target 2023
Gas project AH1-679, Hanover County
Gas · Doswell Limited Partnership
20.0 MWIn study Hanover, VAPJM Apr 2025
Solar project AH2-399, Rockingham County
Solar
20.0 MWIn study Rockingham, VAPJM Mar 2022target 2026
Solar project AH1-071, Powhatan County
Solar · Virginia Electric and Power Company
20.0 MWIn study Powhatan, VAPJM Feb 2025target 2023
Solar project AH2-046, Mecklenburg County
Solar
20.0 MWIn study Mecklenburg, VAPJM Dec 2021target 2025
Railroad Energy Center
Battery storage · Railroad Energy Center, LLC
20.0 MWIn study Prince William, VAPJM Feb 2025target 2022
Solar project AH2-400, Rockingham County
Solar
20.0 MWIn study Rockingham, VAPJM Mar 2022target 2026
Solar project AH1-073, Dickenson County
Solar · Bold Camp CF Solar, LLC
20.0 MWIn study Dickenson, VAPJM Feb 2025target 2024
Alexandria
Other · Reworld REC LLC
20.0 MWIn study Arlington, VAPJM Feb 2025target 2020
Solar project AH2-100, Prince Edward County
Solar
20.0 MWIn study Prince Edward, VAPJM Jan 2022target 2023
Bethlehem Energy Center
Battery storage · Bethlehem Energy Center, LLC
20.0 MWIn study Prince William, VAPJM Feb 2025target 2022
Solar project AH1-138, City Of Williamsburg County
Solar · Virginia Electric and Power Company
20.0 MWIn study City Of Williamsburg, VAPJM Feb 2025target 2022
Solar project AH1-397, King And Queen County
Solar · Ameresco Inc
19.7 MWIn study King And Queen, VAPJM Feb 2025target 2023
Gas project AI2-020, Warren County
Gas
19.0 MWIn study Warren, VAPJM Dec 2022target 2022
Jarratt Energy Facility 2
Solar · Jarratt Energy Facility, LLC
18.0 MWIn study Greensville, VAPJM Mar 2020target 2022
Solar project AI2-345, Amherst County
Solar
18.0 MWIn study Amherst, VAPJM Mar 2023target 2025
Solar project AG2-095, Prince George County
Solar · Virginia Electric and Power Company
18.0 MWIn study Prince George, VAPJM Feb 2025target 2023
Solar project AI2-344, Nelson County
Solar
17.0 MWIn study Nelson, VAPJM Mar 2023target 2024
Solar project AJ1-021, Caroline County
Solar
16.2 MWIn study Caroline, VAPJM Jun 2023target 2029
Solar project AH1-637, Westmoreland County
Solar · SOLAR VA 2019 LLC
16.0 MWIn study Westmoreland, VAPJM Feb 2025target 2022

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20172025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)