United States › Grid › Interconnection queues › Virginia
SOLAR + STORAGE · PJMSolar + storage project AH2-268, Dinwiddie County
Solar + storage project AH2-268, Dinwiddie County is a 37.0 MW solar + storage request in interconnection study in the PJM interconnection queue, in Dinwiddie County, Virginia, connecting to Dominion.
- PlanningQueued Mar 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-268
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Sapony 34.5 kV
- Location
- Dinwiddie County, Virginia
- Technology
- Solar: 37.0 MW · Battery
- Total requested
- 37.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 10 March 2022
- Proposed online date
- July 2025
Location
Marker shows the centre of Dinwiddie County; the queue data does not give exact sites.
Other requests in Dinwiddie County
- Solar project AE2-313, Dinwiddie CountySolar · 314 MW · withdrawn
- Solar project AE1-235, Dinwiddie CountySolar · 180 MW · withdrawn
- Battery storage project AG1-449, Dinwiddie CountyBattery storage · 122 MW · withdrawn
- Battery storage project AG2-506, Dinwiddie CountyBattery storage · 100 MW · withdrawn
- Reams SolarSolar · 80.0 MW · withdrawn
- Battery storage project AF1-266, Dinwiddie CountyBattery storage · 74.5 MW · withdrawn
- Solar + storage project AE1-249, Dinwiddie CountySolar + storage · 70.0 MW · withdrawn
- DW-Lew Jones SolarSolar · 20.0 MW · withdrawn
- Solar project AI2-032, Dinwiddie CountySolar · 20.0 MW · withdrawn
- Solar + storage project AF2-108, Dinwiddie CountySolar + storage · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem