🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA — page 38

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,141423.2 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,141 requests · page 38 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
West Lorain Power Plant 345 kV
Gas
33.0 MWAgreement signed Lorain, OHPJM Oct 2019target 2031
Escondido Energy Center 2
Battery storage
33.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2030
Capricorn I & III repower
Onshore wind · Nextera
32.0 MWAgreement signed Sterling, TXERCOT Mar 2017target 2026
Pitts Dudik II
Solar · Pitts Dudik II
30.2 MWAgreement signed Hill, TXERCOT Jul 2022target 2026
Onshore wind project C2-13, Carbon County
Onshore wind · PacifiCorp
30.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Scioto Solar
Solar
30.0 MWAgreement signed Hardin, OHPJM Mar 2019target 2026
Solar project GI-2010-4, Alamosa County
Solar
30.0 MWAgreement signed Alamosa, COWest Feb 2010target 2012
Solar project 337, Lake County
Solar
30.0 MWAgreement signed Lake, TNSoutheast Jan 2018target 2020
Solar + storage project 783, Natrona County
Solar + storage · Dinosolar, LLC
30.0 MWAgreement signed Natrona, WYWest Aug 2016target 2024
Enchanted Rock NEWPP
Gas · Generate ER-NG, LLC
30.0 MWAgreement signed Harris, TXERCOT Nov 2021target 2026
South Orchard
Battery storage
30.0 MWAgreement signed Cumberland, NJPJM Sep 2019target 2028
Glen Falls Facility
Gas
30.0 MWAgreement signed Harrison, WVPJM Sep 2016target 2029
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023
Onshore wind project J1470, Benton County
Onshore wind
30.0 MWAgreement signed Benton, INMISO Apr 20192020
Battery storage project J466, Huron County
Battery storage
30.0 MWAgreement signed Huron, MIMISO May 2015target 2015
Geothermal project Company LR, Lander County
Geothermal
29.0 MWAgreement signed Lander, NVWest Sep 2021target 2024
Geothermal project IA-PNM-2015-01, Doña Ana Cty County
Geothermal · ORNI 24
29.0 MWAgreement signed Doña Ana Cty, NMWest Jul 2015target 2021
Gas project GEN-2020-061, Cass County
Gas
29.0 MWAgreement signed Cass, MOSPP Apr 2020target 2026
Solar project 572354, Cherokee County
Solar
28.3 MWAgreement signed Cherokee, SCSoutheast Jun 2022target 2027
Onshore wind project C2-14, Carbon County
Onshore wind · PacifiCorp
28.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Other project GEN-2024-GR4, Cherokee County
Other
27.1 MWAgreement signed Cherokee, KSSPP Jul 2024target 2026
Hydro project E291
Hydro
27.0 MWAgreement signed TXMISO May 20122020
Hydro project 323, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2022
Hydro project 322, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2021
Onshore wind project C2-11, Carbon County
Onshore wind · PacifiCorp
26.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Hydro project Q63, Kootenai County
Hydro
26.0 MWAgreement signed Kootenai, IDWest target 2028
Gas project PP00012, Wayne County
Gas
26.0 MWAgreement signed Wayne, NCSoutheast Apr 2025target 2025
Gas project 904269, Wayne County
Gas · Duke Energy Progress, LLC
26.0 MWAgreement signed Wayne, NCSoutheast Jun 2023
Hydro project 63, Kootenai County
Hydro
26.0 MWAgreement signed Kootenai, IDWest Jun 2018target 2028
Gas project GI-116, New Madrid County
Gas
26.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Gas project J1798, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Jun 2020target 2023
Battery storage project J1323, Lagrange County
Battery storage
25.0 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Decatur Battery Storage
Battery storage · Decatur Storage LLC
25.0 MWAgreement signed Van Buren, MIPJM Aug 2020target 2029
Battery storage project J1602, Ouachita Parish County
Battery storage
25.0 MWAgreement signed Ouachita Parish, LAMISO Nov 2021target 2024
Onshore wind project GEN-2019-001, Pratt County
Onshore wind
25.0 MWAgreement signed Pratt, KSSPP Nov 20182025
Gas project J1262, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Apr 2019target 2022
Hayhurst Texas Solar
Solar · Hayhurst Texas Solar, LLC
24.8 MWAgreement signed Culberson, TXERCOT Aug 2020target 2025
Dynamo Solar
Solar
24.5 MWAgreement signed Napa, CACAISO Apr 2019target 2027
Solar + storage project J1200, Putnam County
Solar + storage
24.2 MWAgreement signed Putnam, ILMISO Apr 2019target 2024
Gas project GI-2020-05, Weld County
Gas
24.0 MWAgreement signed Weld, COWest Mar 2020target 2020
Gas project 332, Shelby County
Gas
23.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2018
Solar project J1814, Dickinson County
Solar
22.5 MWAgreement signed Dickinson, MIMISO Jun 2020target 2026
Battery storage project 461, Loudon County
Battery storage
22.0 MWAgreement signed Loudon, TNSoutheast Nov 2020target 2024
Other project GEN-2023-SR1, Brown County
Other
21.9 MWAgreement signed Brown, NESPP Dec 20222024
Hydro project LGE-GIS-2011-003, Jefferson County
Hydro
21.0 MWAgreement signed Jefferson, KYSoutheast Feb 2011target 2013
Gas project J384, Dane County
Gas
21.0 MWAgreement signed Dane, WIMISO Aug 2014target 2017
Wise County Power Repower (CT1, CT2)
Gas · Wise County Power Company LLC
21.0 MWAgreement signed Wise, TXERCOT Jul 2019target 2026
Solar project Q246, Yuma County
Solar
20.0 MWAgreement signed Yuma, AZWest Sep 2016target 2021
Farmers Valley Solar
Solar
20.0 MWAgreement signed Bradford, PAPJM Mar 2020target 2028
Missouri Avenue Battery Storage Project
Battery storage · Calpine Mid-Atlantic Development, LLC
20.0 MWAgreement signed Atlantic, NJPJM Nov 2019target 2028
Page 38 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)