Pitts Dudik II

Pitts Dudik II is a 30.2 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Hill County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2022 (completed)
  2. ConsentedJun 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0364
Grid region
ERCOT (Texas)
Developer
Pitts Dudik II
Connection point (POI)
138 kV Ash Creek Switch (#3473)
Location
Hill County, Texas
Technology
Solar: 30.2 MW
Total requested
30.2 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
18 July 2022
Agreement signed
13 June 2024
Proposed online date
March 2026

Location

Marker shows the centre of Hill County; the queue data does not give exact sites.