United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTPitts Dudik II
Pitts Dudik II is a 30.2 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Hill County, Texas.
Queue statusConsented
- PlanningQueued Jul 2022 (completed)
- ConsentedJun 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0364
- Grid region
- ERCOT (Texas)
- Developer
- Pitts Dudik II
- Connection point (POI)
- 138 kV Ash Creek Switch (#3473)
- Location
- Hill County, Texas
- Technology
- Solar: 30.2 MW
- Total requested
- 30.2 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 18 July 2022
- Agreement signed
- 13 June 2024
- Proposed online date
- March 2026
Location
Marker shows the centre of Hill County; the queue data does not give exact sites.
Other requests in Hill County
- Compadre SolarSolar · 406 MW · agreement signed
- Blue Skies BESSBattery storage · 306 MW · agreement signed
- Aquilla Lake 3 WindOnshore wind · 297 MW · agreement signed
- OCI Cobb Creek SolarSolar + storage · 203 MW · agreement signed
- OCI Cobb Creek ESSSolar + storage · 202 MW · agreement signed
- Padrino SolarSolar · 201 MW · agreement signed
- High Noon SolarSolar + storage · 182 MW · agreement signed
- Vial BESSBattery storage · 135 MW · agreement signed
- Three W SolarSolar · 111 MW · agreement signed
- Midpoint SolarSolar · 98.3 MW · agreement signed
- High Noon StorageSolar + storage · 94.0 MW · agreement signed
- Payne BattlecreekSolar · 85.0 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem