Withdrawn queue requests in the USA — page 37

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 37 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project L06, York County
Gas
550 MWWithdrawn / abandoned York, PAPJM Oct 2003target 2006
Gas project C04, Charles County
Gas
550 MWWithdrawn / abandoned Charles, MDPJM Jan 2000
Gas project D20, Lancaster County
Gas
550 MWWithdrawn / abandoned Lancaster, PAPJM Jul 2000target 2005
NY Hydro-Kinetic Project 1
Hydro · Hydroelectric Corporation
550 MWWithdrawn / abandoned Kings, NYNYISO Jan 2020
Gas project D28, Philadelphia County
Gas
550 MWWithdrawn / abandoned Philadelphia, PAPJM Jul 2000
Madison Bell Energy Center
Gas · Madison Bell Partners LP
550 MWWithdrawn / abandoned ERCOT Aug 2007target 2050
Gas project GEN-2001-022, Pittsburg County
Gas
550 MWWithdrawn / abandoned Pittsburg, OKSPP Jun 2001
Ses Solar Three
Solar
550 MWWithdrawn / abandoned San Bernardino, CACAISO Jun 2006target 2011
Coal project G528, Columbia County
Coal
550 MWWithdrawn / abandoned Columbia, WIMISO Jun 2005target 2011
Coal project IC-121, Early County
Coal
550 MWWithdrawn / abandoned Early, GASoutheast
Gas project D26, Mercer County
Gas
550 MWWithdrawn / abandoned Mercer, NJPJM Jul 2000
Other project 161, Fayette County
Other
550 MWWithdrawn / abandoned Fayette, TNSoutheast May 2001
Cross Hudson Project
Gas · In-City I, LLC
550 MWWithdrawn / abandoned New York, NYNYISO May 2001
Gas project GEN-2007-054, Lea County
Gas
550 MWWithdrawn / abandoned Lea, NMSPP Dec 2007target 2013
Gas project C4-082, Juab County
Gas
550 MWWithdrawn / abandoned Juab, UTWest May 2024target 2028
Gas project D15, New Castle County
Gas
550 MWWithdrawn / abandoned New Castle, DEPJM Jul 2000
Coal project G522, Portage County
Coal
550 MWWithdrawn / abandoned Portage, WIMISO May 2005target 2005
Coal project GEN-2003-007, Jasper County
Coal
550 MWWithdrawn / abandoned Jasper, MOSPP Jul 2003target 2009
Solar project GEN-2018-045, Banner County
Solar
550 MWWithdrawn / abandoned Banner, NESPP May 20182021
South Point Energy Center
Gas
550 MWWithdrawn / abandoned Mohave, AZCAISO Aug 2006target 2009
Gas project C14, Indiana County
Gas
550 MWWithdrawn / abandoned Indiana, PAPJM Mar 2000
Gas project IC-076, Glynn County
Gas
550 MWWithdrawn / abandoned Glynn, GASoutheast
Gas project C03, Charles County
Gas
550 MWWithdrawn / abandoned Charles, MDPJM Jan 2000target 2003
Gas project Q26, Salem County
Gas
550 MWWithdrawn / abandoned Salem, NJPJM Mar 2006target 2008
Solar + storage project Company OG, Lander County
Solar + storage
550 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2028
Gas project J389, Rock County
Gas
550 MWWithdrawn / abandoned Rock, WIMISO Sep 2014
Gas project C12, Harford County
Gas
550 MWWithdrawn / abandoned Harford, MDPJM Mar 2000target 2004
Gas project P02, Muskingum County
Gas
550 MWWithdrawn / abandoned Muskingum, OHPJM Aug 2005target 2007
Gas project AE1-119, Wood County
Gas
550 MWWithdrawn / abandoned Wood, OHPJM Sep 2018target 2022
Gas project B16, Charles County
Gas
550 MWWithdrawn / abandoned Charles, MDPJM Jul 1999target 2004
Combined Cycle
Gas
550 MWWithdrawn / abandoned Bristol, MAISO-NE May 2007target 2010
Gas project W4-024, Hudson County
Gas
550 MWWithdrawn / abandoned Hudson, NJPJM Dec 2010target 2014
Combined Cycle
Gas
550 MWWithdrawn / abandoned Litchfield, CTISO-NE Dec 2006target 2010
Gas project GEN-2009-007, Midland County
Gas
550 MWWithdrawn / abandoned Midland, TXSPP Feb 2009target 2012
Gas project P05, York County
Gas
550 MWWithdrawn / abandoned York, PAPJM Sep 2005target 2008
Gas project B15, Charles County
Gas
550 MWWithdrawn / abandoned Charles, MDPJM Jul 1999target 2003
Gas project IC-046, Decatur County
Gas
550 MWWithdrawn / abandoned Decatur, GASoutheast
Solar project GEN-2023-240, Bailey County
Solar
550 MWWithdrawn / abandoned Bailey, TXSPP Oct 2023target 2030
Gas project D16, Dauphin County
Gas
550 MWWithdrawn / abandoned Dauphin, PAPJM Jul 2000
Gas project D22, Cambria County
Gas
550 MWWithdrawn / abandoned Cambria, PAPJM Jul 2000target 2005
Coal project G523, Marathon County
Coal
550 MWWithdrawn / abandoned Marathon, WIMISO May 2005target 2006
Cross Hudson
Gas · In-City, LLC
550 MWWithdrawn / abandoned NYNYISO Aug 2007
Gas project C13, Harford County
Gas
550 MWWithdrawn / abandoned Harford, MDPJM Mar 2000target 2004
Gas project IC-119, Chatham County
Gas
550 MWWithdrawn / abandoned Chatham, GASoutheast
Gas project GEN-2006-009, Caddo Parish County
Gas
550 MWWithdrawn / abandoned Caddo Parish, LASPP Feb 2006target 2008
Gas project AA2-111, Lancaster County
Gas
550 MWWithdrawn / abandoned Lancaster, PAPJM Apr 2015target 2019
Solar project J3513, Acadia Parish County
Solar
550 MWWithdrawn / abandoned Acadia Parish, LAMISO Apr 2024target 2028
Gas project IC-097, Tift County
Gas
550 MWWithdrawn / abandoned Tift, GASoutheast
CC Administrative Increase
Gas
550 MWWithdrawn / abandoned Hampden, MAISO-NE Aug 2011
Gas project D27, Burlington County
Gas
550 MWWithdrawn / abandoned Burlington, NJPJM Jul 2000target 2004
Page 37 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)