Cross Hudson Project

Cross Hudson Project is a 550 MW gas request withdrawn in the NYISO interconnection queue, in New York County, New York, connecting to CONED.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2001 (completed)
  2. Withdrawn / abandonedAug 2007 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
93
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
In-City I, LLC
Connection point (POI)
W49th Street 345kV
Location
New York County, New York
Technology
Gas: 550 MW
Total requested
550 MW
Queue status
Withdrawn
Entered queue
11 May 2001
Withdrawn
August 2007

Location

Marker shows the centre of New York County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in New York County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem