East River Repowering

East River Repowering is a 288 MW gas request built and operating in the NYISO interconnection queue, connecting to CONED.

Queue statusOperating
  1. PlanningQueued Aug 1999 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
25
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
Consolidated Edison of NY
Connection point (POI)
E. 13th St. 138kV
Location
New York
Technology
Gas: 288 MW
Total requested
288 MW
Study phase
SRIS, CY01
Queue status
Operational
Entered queue
10 August 1999

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem