United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

GAS Β· NYISO

Harlem River Yards

Harlem River Yards is a 79.9 MW gas request built and operating in the NYISO interconnection queue, connecting to CONED.

Queue statusOperating
  1. PlanningQueued Dec 2000 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
79
Grid region
NYISO (New York)
Utility / transmission owner
CONED
Developer
NYPA
Connection point (POI)
Hell Gate Substation
Location
New York
Technology
Gas: 79.9 MW
Total requested
79.9 MW
Study phase
SRIS,CY01
Queue status
Operational
Entered queue
5 December 2000

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem