United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

GAS Β· PJM

Gas project D26, Mercer County

Gas project D26, Mercer County is a 550 MW gas request withdrawn in the PJM interconnection queue, in Mercer County, New Jersey, connecting to PSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2000 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
D26
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Mercer 230kV
Location
Mercer County, New Jersey
Technology
Gas: 550 MW
Total requested
550 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
31 July 2000

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem