πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

SOLAR Β· PJM

Property #6

Property #6 is a 8.0 MW solar request built and operating in the PJM interconnection queue, in Mercer County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Apr 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
W1-121
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Crosswicks 13kV
Location
Mercer County, New Jersey
Technology
Solar: 8.0 MW
Total requested
8.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
30 April 2010
Proposed online date
January 2012
Came online
December 2011

Location

Marker shows the centre of Mercer County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Mercer County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem