| Project | Capacity | Status |
|---|---|---|
| Solar project 962964, Hoke County Solar |
45.0 MW | Withdrawn / abandoned |
| Onshore wind project 140, Glacier County Onshore wind |
45.0 MW | Withdrawn / abandoned |
| Wind Project Onshore wind |
45.0 MW | Withdrawn / abandoned |
| Solar project J2084, Emmons County Solar |
45.0 MW | Withdrawn / abandoned |
| CPN 3rd Turbine, Inc. (JFK) Gas · Calpine Eastern Corporation |
45.0 MW | Withdrawn / abandoned |
| Solar project 399, Crook County Solar · CBG Portland, LLC |
45.0 MW | Withdrawn / abandoned |
| Hydro project Y3-120, Harford County Hydro |
45.0 MW | Withdrawn / abandoned |
| Wood Duck 100 MW Solar · Wood Duck Solar LLC |
45.0 MW | Withdrawn / abandoned |
| Horse Run Solar I Solar + storage |
45.0 MW | Withdrawn / abandoned |
| Solar project 918003, Hoke County Solar |
45.0 MW | Withdrawn / abandoned |
| Onshore wind project H049, Stearns County Onshore wind |
45.0 MW | Withdrawn / abandoned |
| Solar + storage project AH2-208, Lee County Solar + storage |
45.0 MW | Withdrawn / abandoned |
| Big Break Energy Storage Battery storage |
45.0 MW | Withdrawn / abandoned |
| Solar project AG2-432, Wythe County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project AF1-044, Allegany County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project IC-519, Webb County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project AF2-186, Paulding County Solar |
45.0 MW | Withdrawn / abandoned |
| Geothermal project Company JG, Washoe County Geothermal |
45.0 MW | Withdrawn / abandoned |
| Battery storage project J3492, Posey County Battery storage |
45.0 MW | Withdrawn / abandoned |
| El Patrimonio Solar 2 Solar · Heritage Solar, LLC |
45.0 MW | Withdrawn / abandoned |
| Opal Solar Solar · Innovative Solar 165 |
45.0 MW | Withdrawn / abandoned |
| Solar project 620, Lake County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project J220, Monroe County Solar |
45.0 MW | Withdrawn / abandoned |
| Geothermal project G0497, Cassia County Geothermal |
45.0 MW | Withdrawn / abandoned |
| Solar project 991, Tooele County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project G0627, Klickitat County Solar |
45.0 MW | Withdrawn / abandoned |
| 2W Whatley Phase 1 Onshore wind · TripleT Renewable Enrgy Solutions, LLC |
45.0 MW | Withdrawn / abandoned |
| Central Solar Park Onshore wind |
45.0 MW | Withdrawn / abandoned |
| Solar project IC-642, Turner County Solar |
45.0 MW | Withdrawn / abandoned |
| Kce NY 28 Battery storage · KCE NY 28, LLC |
45.0 MW | Withdrawn / abandoned |
| Citrine Solar Solar · Innovative Solar 145 |
45.0 MW | Withdrawn / abandoned |
| Stonycreek Onshore wind |
45.0 MW | Withdrawn / abandoned |
| SP-TX-09 Solar · Solar Prime |
45.0 MW | Withdrawn / abandoned |
| GNA Energy Gas · GNA Energy, LLC |
45.0 MW | Withdrawn / abandoned |
| Daphne Storage Battery storage · Hanwha Q CELLS USA |
45.0 MW | Withdrawn / abandoned |
| Solar + storage project AF2-055, Northampton County Solar + storage |
45.0 MW | Withdrawn / abandoned |
| Geothermal project Company HO, Pershing County Geothermal |
45.0 MW | Withdrawn / abandoned |
| Solar project AG2-183, Hardin County Solar |
45.0 MW | Withdrawn / abandoned |
| Kce NY 28 Battery storage · KCE NY 28, LLC |
45.0 MW | Withdrawn / abandoned |
| Solar Solar |
45.0 MW | Withdrawn / abandoned |
| Messenger Brothers Storage Battery storage · RWE Solar Development, LLC |
45.0 MW | Withdrawn / abandoned |
| Solar project AE2-026, Louisa County Solar |
44.8 MW | Withdrawn / abandoned |
| Solar project AF1-079, Louisa County Solar |
44.8 MW | Withdrawn / abandoned |
| Solar + storage project AH2-152, Monroe County Solar + storage |
44.8 MW | Withdrawn / abandoned |
| California Bear 6 Solar + storage |
44.8 MW | Withdrawn / abandoned |
| Solar project 953801, Robeson County Solar |
44.5 MW | Withdrawn / abandoned |
| Tobin Solar + storage |
44.4 MW | Withdrawn / abandoned |
| HappyDogStorage Battery storage · Rosula Solar LLC |
44.3 MW | Withdrawn / abandoned |
| Onshore wind project J3854, Mason County Onshore wind |
44.3 MW | Withdrawn / abandoned |
| Gas project 91, Coos County Gas |
44.2 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)