BATTERY STORAGE Β· ERCOT

HappyDogStorage

HappyDogStorage is a 44.3 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
26INR0658
Grid region
ERCOT (Texas)
Developer
Rosula Solar LLC
Connection point (POI)
Tap 345kV 3704 Hog Creek Switch β€šΓ„Γ¬ 3687 Bell County East Switch
Technology
Battery: 44.3 MW
Total requested
44.3 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Proposed online date
April 2027

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem