HYDRO Β· PJM

Hydro project Y3-120, Harford County

Hydro project Y3-120, Harford County is a 45.0 MW hydro request withdrawn in the PJM interconnection queue, in Harford County, Maryland, connecting to PECO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2013 (completed)
  2. Withdrawn / abandonedSep 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Y3-120
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PECO
Connection point (POI)
Conowingo 230kV
Location
Harford County, Maryland
Technology
Hydro: 45.0 MW
Total requested
45.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
30 April 2013
Proposed online date
June 2016
Withdrawn
September 2013

Location

Marker shows the centre of Harford County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Harford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem