United States βΊ Grid βΊ Interconnection queues βΊ Nevada
GEOTHERMAL Β· WESTGeothermal project Company HO, Pershing County
Geothermal project Company HO, Pershing County is a 45.0 MW geothermal request withdrawn in the West interconnection queue, in Pershing County, Nevada, connecting to NV Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2017 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Company HO
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- Pershing County, Nevada
- Technology
- Geothermal: 45.0 MW
- Total requested
- 45.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 18 September 2017
- Proposed online date
- November 2026
Location
Marker shows the centre of Pershing County; the queue data does not give exact sites.
Other requests in Pershing County
- Geothermal project Company LB, Pershing CountyGeothermal Β· 115 MW Β· agreement signed
- Solar project Company IH, Pershing CountySolar Β· 80.0 MW Β· agreement signed
- Solar + storage project Company QC, Pershing CountySolar + storage Β· 200 MW Β· in study
- Geothermal project 25-00389, Pershing CountyGeothermal Β· 38.5 MW Β· in study
- Geothermal project 25-00425, Pershing CountyGeothermal Β· 31.0 MW Β· in study
- Geothermal project Company RA, Pershing CountyGeothermal Β· 20.0 MW Β· in study
- Geothermal project Company RD, Pershing CountyGeothermal Β· 19.9 MW Β· in study
- Geothermal project 25N-SG2, Pershing CountyGeothermal Β· 19.8 MW Β· in study
- Solar + storage project Company NP, Pershing CountySolar + storage Β· 480 MW Β· suspended
- Solar + storage project Company JX, Pershing CountySolar + storage Β· 340 MW Β· suspended
- Solar + storage project Company LL, Pershing CountySolar + storage Β· 300 MW Β· suspended
- Solar + storage project Company HQ, Pershing CountySolar + storage Β· 240 MW Β· suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem