United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas (2022 requests) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown29358.6 GW
Active in queue58.6 GW293 requests
Agreement signed23.9 GW116 requests
Withdrawn8117.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

293 requests · page 3 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Diamondback BESS
Battery storage
204 MWPaused / redesign Starr, TXERCOT Mar 2022
Mercury Solar III
Solar + storage · Mercury Solar
204 MWIn study Hill, TXERCOT Aug 2022target 2029
Owens Solar
Solar · Owens Solar LLC
204 MWPaused / redesign Bosque, TXERCOT Feb 2022target 2025
Glasgow Solar
Solar + storage · Glasgow Solar LLC
204 MWAgreement signed Navarro, TXERCOT Feb 2022target 2027
Timberlakes Solar
Solar · Donegalsol
204 MWIn study Dickens, TXERCOT Nov 2022target 2026
OCI Cobb Creek Solar
Solar + storage · Hillsboro Solar Project LLC
203 MWAgreement signed Hill, TXERCOT Nov 2022target 2027
Sunlight Solar
Solar
203 MWPaused / redesign Ector, TXERCOT Jun 2022target 2027
Alexandrite Storage
Battery storage · Johnson Energy Storage, LLC
203 MWIn study Cameron, TXERCOT Jun 2022target 2026
Wolf Spring Storage
Solar + storage · Wolf Spring Solar, LLC
203 MWAgreement signed Dickens, TXERCOT Dec 2022target 2028
Legato BESS
Battery storage · Legato Storage, LLC
203 MWIn study Wise, TXERCOT Sep 2022target 2028
Fortissimo BESS
Battery storage · Fortissimo BESS, LCC
203 MWIn study Montague, TXERCOT Oct 2022target 2028
Fiji Solar
Solar
203 MWPaused / redesign Limestone, TXERCOT Sep 2022
McMEXICO STORAGE
Battery storage · FRESH AIR ENERGY II, LLC
202 MWIn study Hidalgo, TXERCOT Feb 2022target 2028
Hacienda Storage
Battery storage · Galveston Energy Storage LLC
202 MWIn study Galveston, TXERCOT May 2022target 2026
Staccato BESS
Battery storage · Staccato Storage, LLC
202 MWIn study Fayette, TXERCOT Nov 2022target 2026
Mitchell Plant Road Storage
Battery storage
202 MWPaused / redesign Pecos, TXERCOT Feb 2022
Goldeneye BESS
Battery storage · Black Mountain Energy Storage II
202 MWAgreement signed Bell, TXERCOT Jun 2022target 2028
OCI Cobb Creek ESS
Solar + storage · Hillsboro Solar Project LLC
202 MWAgreement signed Hill, TXERCOT Dec 2022target 2027
Mitchell Plant Road Solar
Solar
202 MWPaused / redesign Pecos, TXERCOT Feb 2022target 2025
Padrino Solar
Solar · Hill Solar II, LLC
201 MWAgreement signed Hill, TXERCOT Sep 2022target 2026
Eldora BESS
Solar + storage · Eldora Energy LLC
201 MWAgreement signed Matagorda, TXERCOT Jun 2022target 2028
Nockenut Springs Solar 4
Solar · Pecan Springs Energy, LLC
201 MWIn study Gonzales, TXERCOT Sep 2022target 2029
Apache Hill BESS
Battery storage · APACHE HILL ENERGY CENTER
201 MWAgreement signed Hood, TXERCOT Nov 2022target 2026
Seragio BESS
Battery storage · Seragio BESS, LLC
201 MWIn study Ector, TXERCOT Sep 2022target 2027
Jasper BESS
Battery storage · Jasper BESS, LLC
201 MWIn study Midland, TXERCOT Sep 2022target 2028
Blue Heron BESS
Battery storage · Blue Heron BESS, LLC
201 MWIn study Reeves, TXERCOT Oct 2022target 2028
Champaign BESS
Battery storage · Champaign BESS, LLC
201 MWAgreement signed Glasscock, TXERCOT Sep 2022target 2027
Moonlight Sonata BESS
Battery storage · Samsung Solar Energy 2, LLC
201 MWIn study Colorado, TXERCOT Sep 2022target 2028
De Los Santos
Battery storage · BRP De Los Santos BESS LLC
201 MWIn study Maverick, TXERCOT May 2022target 2027
Smokey Willie Solar SLF
Solar + storage · Neches Solar, LLC
201 MWIn study Anderson, TXERCOT Jan 2022target 2028
Possum Kingdom BESS
Solar + storage · PK Solar, LLC
201 MWIn study Jack, TXERCOT Sep 2022target 2027
Eldora Solar
Solar + storage · Eldora Energy LLC
201 MWAgreement signed Matagorda, TXERCOT Jun 2022target 2028
Sloan Storage
Battery storage · Sloan Energy Storage LLC
201 MWIn study Henderson, TXERCOT Feb 2022target 2026
APV Plumwood Storage
Battery storage · APV Lonestar Energy LLC
201 MWAgreement signed Chambers, TXERCOT Mar 2022target 2027
Trelas
Battery storage · Trelasol, LLC
201 MWIn study Mcculloch, TXERCOT Sep 2022target 2028
Forts Trail Solar
Solar + storage · JC Central Bluff, LLC
201 MWIn study Taylor, TXERCOT Jun 2022target 2028
HGP Pacesetter BESS
Battery storage
201 MWPaused / redesign Dallas, TXERCOT Sep 2022
Erika Solar
Solar + storage · Erika Solar, LLC
201 MWAgreement signed Kaufman, TXERCOT Jul 2022target 2027
Bar Candela Solar SLF
Solar + storage · Bar Candela Solar Project LLC
200 MWAgreement signed Freestone, TXERCOT Mar 2022target 2027
Triangle Ranch Bravo
Onshore wind · Triangle Ranch Wind
200 MWIn study Cottle, TXERCOT Oct 2022target 2028
Triangle Ranch Charlie
Onshore wind
200 MWPaused / redesign Cottle, TXERCOT Sep 2022target 2025
PSE Chihuahua TX Storage
Battery storage · PureSky Development Inc
200 MWIn study Hidalgo, TXERCOT Dec 2022target 2027
Battery storage project J3169, Hardin County
Battery storage
200 MWIn study Hardin, TXMISO Sep 2022target 2026
PSE Flores TX Storage
Battery storage · PureSky Development Inc
200 MWIn study Starr, TXERCOT Dec 2022target 2027
Borderland ESC
Battery storage · FRESH AIR ENERGY II, LLC
200 MWIn study Hidalgo, TXERCOT Feb 2022target 2026
Camino Santiago Solar
Solar · Camino Solar Project, LLC
196 MWAgreement signed Milam, TXERCOT Sep 2022target 2027
Wolf Spring Solar
Solar + storage · Wolf Spring Solar, LLC
196 MWAgreement signed Dickens, TXERCOT Dec 2022target 2028
Argenta Storage
Solar + storage · Charter Oak Storage, LLC
192 MWAgreement signed Bee, TXERCOT Jun 2022target 2028
Harryoung Solar
Solar + storage · Gransolar Texas Four LLC
190 MWIn study Cameron, TXERCOT Nov 2022target 2028
Blanket Ranch North Solar
Solar + storage · Blanket Ranch North Solar, LLC
189 MWIn study Brown, TXERCOT Jun 2022target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)