πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2019 requests) β€” page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13020.0 GW
Active in queue20.0 GW130 requests
Agreement signed14.3 GW90 requests
Withdrawn15321.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

130 requests Β· page 3 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1359, Linn County
Gas
95.0 MWIn study Linn, IAMISO Apr 2019target 2025
Solar project J1399, Ingham County
Solar
90.0 MWAgreement signed Ingham, MIMISO Apr 2019target 2025
Solar project J1209, Saline County
Solar
80.0 MWAgreement signed Saline, ILMISO Apr 2019target 2023
Solar project J1208, Saline County
Solar
80.0 MWAgreement signed Saline, ILMISO Apr 2019target 2023
Battery storage project J1411, Dane County
Battery storage
75.0 MWAgreement signed Dane, WIMISO Apr 2019target 2025
Solar project J1475, Clark County
Solar
75.0 MWAgreement signed Clark, ILMISO Apr 20192024
Solar project J1281, Ashley County
Solar
75.0 MWAgreement signed Ashley, ARMISO Apr 2019target 2024
Battery storage project J1326, Dane County
Battery storage
75.0 MWAgreement signed Dane, WIMISO Apr 2019target 2025
Solar + storage project J1202, Randolph County
Solar + storage
68.4 MWAgreement signed Randolph, ILMISO Apr 2019target 2024
Hydro project J1213, Iron County
Hydro
60.0 MWAgreement signed Iron, MOMISO Apr 2019target 2024
Solar project J1387, Jasper County
Solar
60.0 MWAgreement signed Jasper, INMISO Apr 2019target 2024
Solar + storage project J1198, Jasper County
Solar + storage
51.8 MWAgreement signed Jasper, ILMISO Apr 2019target 2023
Battery storage project J1477, Scott County
Battery storage
50.0 MWAgreement signed Scott, IAMISO Apr 2019target 2024
Battery storage project J1229, Muscatine County
Battery storage
50.0 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026
Battery storage project J1272, Vanderburgh County
Battery storage
50.0 MWUnder construction Vanderburgh, INMISO Apr 2019target 2025
Solar project J1361, Washington Parish County
Solar
50.0 MWUnder construction Washington Parish, LAMISO Apr 20192024
Solar project J1235, Knox County
Solar
50.0 MWAgreement signed Knox, INMISO Apr 2019target 2023
Solar project J1312, Mccook County
Solar
50.0 MWAgreement signed Mccook, SDMISO Apr 2019target 2025
Solar project J1258, Lonoke County
Solar
50.0 MWAgreement signed Lonoke, ARMISO Apr 2019target 2024
Solar project J1210, Iosco County
Solar
50.0 MWAgreement signed Iosco, MIMISO Apr 2019target 2025
Battery storage project J1316, Kenosha County
Battery storage
50.0 MWAgreement signed Kenosha, WIMISO Apr 20192024
Solar + storage project J1201, Montgomery County
Solar + storage
44.2 MWAgreement signed Montgomery, ILMISO Apr 2019target 2024
Onshore wind project J1470, Benton County
Onshore wind
30.0 MWAgreement signed Benton, INMISO Apr 20192020
Battery storage project J1323, Lagrange County
Battery storage
25.0 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Gas project J1262, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Apr 2019target 2022
Solar + storage project J1200, Putnam County
Solar + storage
24.2 MWAgreement signed Putnam, ILMISO Apr 2019target 2024
Battery storage project J1257, Tangipahoa Parish County
Battery storage
20.0 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Battery storage project J1329, Washtenaw County
Battery storage
20.0 MWUnder construction Washtenaw, MIMISO Apr 2019target 2025
Solar + storage project J1199, Fulton County
Solar + storage
20.0 MWAgreement signed Fulton, ILMISO Apr 2019target 2023
Other project J1247, St. Mary Parish County
Other
17.0 MWUnder construction St. Mary Parish, LAMISO Apr 20192023
Page 3 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)