Withdrawn queue requests in SPP (Southwest Power Pool) — page 28

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,846382.9 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,846 requests · page 28 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2006-038N018, Clay County
Onshore wind
100 MWWithdrawn / abandoned Clay, NESPP Oct 2006
Solar project GEN-2016-090, Terry County
Solar
100 MWWithdrawn / abandoned Terry, TXSPP Sep 2016target 2022
Solar project GEN-2019-073, Madison County
Solar
100 MWWithdrawn / abandoned Madison, NESPP May 2019target 2027
Onshore wind project GEN-2008-104, Noble County
Onshore wind
100 MWWithdrawn / abandoned Noble, OKSPP Sep 2008target 2011
Solar + storage project GEN-2021-080, Lea County
Solar + storage
100 MWWithdrawn / abandoned Lea, NMSPP Apr 20212024
Battery storage project GEN-2021-002, Blaine County
Battery storage
100 MWWithdrawn / abandoned Blaine, OKSPP Dec 2020target 2027
Onshore wind project GEN-2009-053, Ford County
Onshore wind
100 MWWithdrawn / abandoned Ford, KSSPP Dec 2009target 2011
Onshore wind project GEN-2014-050, Douglas County
Onshore wind
100 MWWithdrawn / abandoned Douglas, KSSPP Sep 2014target 2016
Onshore wind project GEN-2008-099, Coffey County
Onshore wind
100 MWWithdrawn / abandoned Coffey, KSSPP Aug 2008target 2011
Solar + storage project GEN-2021-085, Ford County
Solar + storage
100 MWWithdrawn / abandoned Ford, KSSPP Apr 2021target 2027
Onshore wind project GEN-2009-065, Graham County
Onshore wind
100 MWWithdrawn / abandoned Graham, KSSPP Dec 2009target 2011
Onshore wind project GEN-2006-038N003, Platte County
Onshore wind
100 MWWithdrawn / abandoned Platte, NESPP Oct 2006
Battery storage project GEN-2021-092, Hansford County
Battery storage
100 MWWithdrawn / abandoned Hansford, TXSPP Apr 2021target 2026
Onshore wind project GEN-2003-001, Dewey County
Onshore wind
100 MWWithdrawn / abandoned Dewey, OKSPP Mar 2003target 2004
Onshore wind project GEN-2007-010N02, Butler County
Onshore wind
100 MWWithdrawn / abandoned Butler, NESPP Mar 2007
Onshore wind project GEN-2006-038N, Cherry County
Onshore wind
100 MWWithdrawn / abandoned Cherry, NESPP Oct 2006
Onshore wind project GEN-2006-038N008, Brown County
Onshore wind
100 MWWithdrawn / abandoned Brown, NESPP Oct 2006
Battery storage project GEN-2022-101, Andrew County
Battery storage
100 MWWithdrawn / abandoned Andrew, MOSPP Jan 2023target 2027
Battery storage project GEN-2023-213, Benton County
Battery storage
100 MWWithdrawn / abandoned Benton, ARSPP Oct 2023target 2028
Onshore wind project GEN-2006-038N022, Antelope County
Onshore wind
100 MWWithdrawn / abandoned Antelope, NESPP Oct 2006
Battery storage project GEN-2019-077, Lancaster County
Battery storage
100 MWWithdrawn / abandoned Lancaster, NESPP May 2019target 2022
Onshore wind project GEN-2006-038N007, Custer County
Onshore wind
100 MWWithdrawn / abandoned Custer, NESPP Oct 2006target 2010
Solar + storage project GEN-2023-162, Delaware County
Solar + storage
100 MWWithdrawn / abandoned Delaware, OKSPP Oct 2023target 2027
Solar project GEN-2022-108, Desoto Parish County
Solar
100 MWWithdrawn / abandoned Desoto Parish, LASPP Jan 2023target 2027
Onshore wind project GEN-2006-038N023, Greeley County
Onshore wind
100 MWWithdrawn / abandoned Greeley, NESPP Oct 2006
Onshore wind project GEN-2008-105, Noble County
Onshore wind
100 MWWithdrawn / abandoned Noble, OKSPP Sep 2011target 2011
Onshore wind project GEN-2008-063, Beaver County
Onshore wind
100 MWWithdrawn / abandoned Beaver, OKSPP Jun 2008target 2012
Solar + storage project GEN-2023-084, Brown County
Solar + storage
100 MWWithdrawn / abandoned Brown, SDSPP Oct 2023target 2028
Onshore wind project GEN-2008-113, Garfield County
Onshore wind
100 MWWithdrawn / abandoned Garfield, OKSPP Sep 2008target 2015
Battery storage project GEN-2018-095, Jackson County
Battery storage
100 MWWithdrawn / abandoned Jackson, MOSPP Nov 2018target 2023
Solar project GEN-2016-080, Lea County
Solar
100 MWWithdrawn / abandoned Lea, NMSPP Jun 2016target 2019
Onshore wind project GEN-2006-038N012, Lancaster County
Onshore wind
100 MWWithdrawn / abandoned Lancaster, NESPP Oct 2006
Battery storage project GEN-2023-181, Logan County
Battery storage
100 MWWithdrawn / abandoned Logan, NDSPP Oct 2023target 2026
Solar project GEN-2022-041, Cowley County
Solar
100 MWWithdrawn / abandoned Cowley, KSSPP Jun 20222025
Onshore wind project GEN-2007-010N05, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, NESPP Mar 2007
Battery storage project GEN-2019-074, Lamb County
Battery storage
100 MWWithdrawn / abandoned Lamb, TXSPP May 20192023
Gas project GEN-2012-026, Thomas County
Gas
100 MWWithdrawn / abandoned Thomas, KSSPP Sep 2012target 2014
Hydro project GEN-2008-094, Wilbarger County
Hydro
100 MWWithdrawn / abandoned Wilbarger, TXSPP Aug 2008target 2011
Onshore wind project GEN-2016-025, Custer County
Onshore wind
100 MWWithdrawn / abandoned Custer, NESPP Mar 2016target 2018
Onshore wind project GEN-2007-010N, Lincoln County
Onshore wind
100 MWWithdrawn / abandoned Lincoln, NESPP Mar 2007
Onshore wind project GEN-2018-053, Jasper County
Onshore wind
100 MWWithdrawn / abandoned Jasper, MOSPP May 20182025
Solar project GEN-2017-110, Grant County
Solar
100 MWWithdrawn / abandoned Grant, KSSPP Nov 2017target 2020
Onshore wind project GEN-2008-035, Canadian County
Onshore wind
100 MWWithdrawn / abandoned Canadian, OKSPP May 2008target 2011
Solar + storage project GEN-2021-104, Bossier Parish County
Solar + storage
100 MWWithdrawn / abandoned Bossier Parish, LASPP May 2021target 2027
Onshore wind project GEN-2006-038N002, Nuckolls County
Onshore wind
100 MWWithdrawn / abandoned Nuckolls, NESPP Oct 2006
Onshore wind project GEN-2006-038N020, Antelope County
Onshore wind
100 MWWithdrawn / abandoned Antelope, NESPP Oct 2006
Battery storage project GEN-2022-153, Burt County
Battery storage
100 MWWithdrawn / abandoned Burt, NESPP Feb 2023target 2026
Onshore wind project GEN-2007-035, Harmon County
Onshore wind
100 MWWithdrawn / abandoned Harmon, OKSPP Sep 2007target 2009
Onshore wind project GEN-2006-038N024, Kearney County
Onshore wind
100 MWWithdrawn / abandoned Kearney, NESPP Oct 2006
Battery storage project GEN-2019-056, Randall County
Battery storage
100 MWWithdrawn / abandoned Randall, TXSPP May 2019target 2027
Page 28 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)