United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 27
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Other project U1-029, Cumberland County Other |
110 MW | Withdrawn / abandoned |
| Solar + storage project AH2-211, St. Joseph County Solar + storage |
110 MW | Withdrawn / abandoned |
| Battery storage project AH1-598, Ashland County Battery storage |
110 MW | Withdrawn / abandoned |
| Solar project AF2-090, Hardin County Solar |
110 MW | Withdrawn / abandoned |
| Solar project AH1-597, Ashland County Solar |
110 MW | Withdrawn / abandoned |
| Gas project X4-018, Hudson County Gas |
110 MW | Withdrawn / abandoned |
| Solar project AG1-061, Sussex County Solar · Deere Acres Solar LLC |
109 MW | Withdrawn / abandoned |
| Solar project AH1-385, Greensville County Solar |
109 MW | Withdrawn / abandoned |
| Other project C01-1013, Charles County Other · Chalk Point Steam, LLC |
108 MW | Withdrawn / abandoned |
| Battery storage project AE2-237, Sussex County Battery storage |
107 MW | Withdrawn / abandoned |
| Battery storage project AH1-731, Prince Edward County Battery storage · Cumberland Solar USA, LLC |
107 MW | Withdrawn / abandoned |
| Battery storage project AF1-303, Atlantic County Battery storage |
107 MW | Withdrawn / abandoned |
| Finneywood Solar Solar · Virginia Electric and Power Company |
107 MW | Withdrawn / abandoned |
| Solar project AG1-048, Amelia County Solar |
106 MW | Withdrawn / abandoned |
| Onshore wind project AG1-509, Grayson County Onshore wind |
105 MW | Withdrawn / abandoned |
| Gas project AD2-165, Middlesex County Gas |
105 MW | Withdrawn / abandoned |
| Gas project AB2-091, Hudson County Gas |
105 MW | Withdrawn / abandoned |
| Solar project AG2-018, Morgan County Solar |
105 MW | Withdrawn / abandoned |
| Other project Z2-069 Other |
105 MW | Withdrawn / abandoned |
| Gas project AF1-043, Clinton County Gas |
105 MW | Withdrawn / abandoned |
| Solar + storage project AH1-769, Putnam County Solar + storage · Marquis Solar LLC |
105 MW | Withdrawn / abandoned |
| Onshore wind project Q39, Henry County Onshore wind |
105 MW | Withdrawn / abandoned |
| Gas project AB2-008, Middlesex County Gas |
105 MW | Withdrawn / abandoned |
| Gas project AF2-012, Montgomery County Gas |
104 MW | Withdrawn / abandoned |
| Gas project AE2-296, Montgomery County Gas |
104 MW | Withdrawn / abandoned |
| Solar project AE1-064, Bedford County Solar |
102 MW | Withdrawn / abandoned |
| Solar project AC1-139, Frederick County Solar |
102 MW | Withdrawn / abandoned |
| Montour Solar One Solar |
102 MW | Withdrawn / abandoned |
| Onshore wind project Y1-031, Clarion County Onshore wind |
102 MW | Withdrawn / abandoned |
| Solar project AF1-335, Berks County Solar |
101 MW | Withdrawn / abandoned |
| Onshore wind project Q24, Potter County Onshore wind |
101 MW | Withdrawn / abandoned |
| Battery storage project AF2-208, Cecil County Battery storage |
101 MW | Withdrawn / abandoned |
| Battery storage project AF2-197, Bradford County Battery storage |
101 MW | Withdrawn / abandoned |
| Onshore wind project W2-044, Whitley County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project N51, Carbon County Onshore wind |
101 MW | Withdrawn / abandoned |
| Solar project AG2-367, Appomattox County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AH1-266, Greensville County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project Y2-010, White County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project AH1-310, Van Buren County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AF1-035, Highland County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project AG1-404, Mclean County Battery storage · Wapella Bluffs Wind Project, LLC |
100 MW | Withdrawn / abandoned |
| Solar project AG1-042, Franklin County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AH2-275, Carroll County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AD2-157, Hampshire County Solar |
100 MW | Withdrawn / abandoned |
| Buck Mountain Wind Farm Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project AG1-437, Bertie County Solar · RWE Solar Development, LLC |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-326, Fairfax County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar + storage project AH1-538, Van Wert County Solar + storage · Riverlake Energy, LLC |
100 MW | Withdrawn / abandoned |
| Other project AC2-033 Other |
100 MW | Withdrawn / abandoned |
| Nittany North Solar Solar + storage · Invenergy Solar Project Development LLC |
100 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)