United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in CAISO (California) — page 26
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Avets Battery storage |
137 MW | Withdrawn / abandoned |
| Capetown Hybrid Onshore wind |
135 MW | Withdrawn / abandoned |
| Sienna Solar + storage |
133 MW | Withdrawn / abandoned |
| Whitehorse Mountain Wind Power Plant Onshore wind |
132 MW | Withdrawn / abandoned |
| Contra Costa Generating Station Expansion Gas |
131 MW | Withdrawn / abandoned |
| Ramos Gas |
131 MW | Withdrawn / abandoned |
| Palmdale Energy Gas |
130 MW | Withdrawn / abandoned |
| Milagro Wind Onshore wind |
130 MW | Withdrawn / abandoned |
| Cassius Storage Battery storage |
130 MW | Withdrawn / abandoned |
| Dog Creek Hybrid Battery storage |
129 MW | Withdrawn / abandoned |
| Mensa Battery storage |
128 MW | Withdrawn / abandoned |
| Solano Wind Project - Phase 3 (115KV) Onshore wind |
128 MW | Withdrawn / abandoned |
| Lowlands P3 Gas |
127 MW | Withdrawn / abandoned |
| Tungsten BESS Battery storage |
126 MW | Withdrawn / abandoned |
| Mayacmas Wind Power Onshore wind |
126 MW | Withdrawn / abandoned |
| Eastside Solar + storage |
124 MW | Withdrawn / abandoned |
| Bonita Batería Battery storage |
124 MW | Withdrawn / abandoned |
| Bonita Batería 2 Battery storage |
124 MW | Withdrawn / abandoned |
| Red Diamond Solar Solar + storage |
124 MW | Withdrawn / abandoned |
| Calcite Solar 1 Solar + storage |
124 MW | Withdrawn / abandoned |
| Pronghorn Energy Storage Battery storage |
123 MW | Withdrawn / abandoned |
| Rancho Fresno Storage Farm Battery storage |
122 MW | Withdrawn / abandoned |
| Normandy Solar + storage |
122 MW | Withdrawn / abandoned |
| Cook Ranch Solar + storage |
121 MW | Withdrawn / abandoned |
| Great Valley Solar 2 Solar |
120 MW | Withdrawn / abandoned |
| Highline Solar Energy Center Solar + storage |
120 MW | Withdrawn / abandoned |
| Sidewinder Solar Solar |
120 MW | Withdrawn / abandoned |
| Little Lake South Wind Farm Onshore wind |
120 MW | Withdrawn / abandoned |
| Great Valley Solar Solar |
120 MW | Withdrawn / abandoned |
| Windstar I Onshore wind |
120 MW | Withdrawn / abandoned |
| Kearny Hybrid Power Solar + storage |
120 MW | Withdrawn / abandoned |
| Ord Mountain Solar + storage |
120 MW | Withdrawn / abandoned |
| American Kings 2 Solar |
120 MW | Withdrawn / abandoned |
| Laurel Mountain Wind Farm Onshore wind |
120 MW | Withdrawn / abandoned |
| GV Solar 3 Solar |
120 MW | Withdrawn / abandoned |
| Grand Ave - Battery System Battery storage |
118 MW | Withdrawn / abandoned |
| Solstice Sun Energy Center Solar + storage |
118 MW | Withdrawn / abandoned |
| Adame 1 Solar |
118 MW | Withdrawn / abandoned |
| Eastshore Energy Facility Project Gas |
118 MW | Withdrawn / abandoned |
| Birch Street - Battery System Battery storage |
118 MW | Withdrawn / abandoned |
| Cuyapaipe Wind Power Project Onshore wind |
117 MW | Withdrawn / abandoned |
| Rocklin Peaker Gas |
117 MW | Withdrawn / abandoned |
| DGC Kelso Re 115.5 Gas |
116 MW | Withdrawn / abandoned |
| Ukiah Energy Center Gas |
115 MW | Withdrawn / abandoned |
| Meadow Ridge Solar And Battery Solar + storage |
114 MW | Withdrawn / abandoned |
| Sequan Battery storage |
113 MW | Withdrawn / abandoned |
| Sodis Storage Battery storage |
112 MW | Withdrawn / abandoned |
| Exchequer Hydro |
112 MW | Withdrawn / abandoned |
| Tyre Solar + storage |
111 MW | Withdrawn / abandoned |
| Westside Renewal PV Project Solar |
110 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)