United States β€Ί Grid β€Ί Interconnection queues β€Ί California

GAS Β· CAISO

Lowlands P3

Lowlands P3 is a 127 MW gas request withdrawn in the CAISO interconnection queue, in Madera County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2004 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
44
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Borden Substation 230 kV Bus
Location
Madera County, California
Technology
Gas: 127 MW
Total requested
127 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
29 November 2004
Proposed online date
October 2007

Location

Marker shows the centre of Madera County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Madera County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem