Solano Wind Project - Phase 3 (115KV)

Solano Wind Project - Phase 3 (115KV) is a 128 MW onshore wind request withdrawn in the CAISO interconnection queue, in Solano County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2006 (completed)
  2. Withdrawn / abandonedAug 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
107
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Brighton-Contra Costa 115 kV
Location
Solano County, California
Technology
Wind: 128 MW
Total requested
128 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
9 June 2006
Proposed online date
March 2011
Withdrawn
August 2011

Location

Marker shows the centre of Solano County; the queue data does not give exact sites.