🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 254

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 254 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG2-473, Cass County
Solar
100 MWWithdrawn / abandoned Cass, MIPJM Mar 2021target 2025
Keyhole Wind 2
Onshore wind
100 MWWithdrawn / abandoned Kern, CACAISO Apr 2020target 2024
Solar + storage project 1051, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2021
Solar + storage project IA-PNM-2021-11, San Juan County
Solar + storage
100 MWWithdrawn / abandoned San Juan, NMWest Jul 2021target 2025
Onshore wind project J729, Clark County
Onshore wind
100 MWWithdrawn / abandoned Clark, SDMISO Nov 2016target 2019
Battery storage project J2459, Jefferson County
Battery storage
100 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Solar project J1418, Pulaski County
Solar
100 MWWithdrawn / abandoned Pulaski, ILMISO Apr 2019target 2021
Solar + storage project C2-128, Yakima County
Solar + storage
100 MWWithdrawn / abandoned Yakima, WAWest May 2022target 2025
Solar project LGE-GIS-2019-030, Hardin County
Solar
100 MWWithdrawn / abandoned Hardin, KYSoutheast Nov 2019target 2021
Onshore wind project G0422, Wheeler County
Onshore wind
100 MWWithdrawn / abandoned Wheeler, ORWest Apr 2010target 2013
Onshore wind project G491, Pipestone County
Onshore wind
100 MWWithdrawn / abandoned Pipestone, MNMISO Dec 2004target 2010
Honey Ridge Solar
Solar · Honey Ridge Solar 1, LLC
100 MWWithdrawn / abandoned Jefferson, NYNYISO Sep 2024
Solar project AH1-651, Southampton County
Solar
100 MWWithdrawn / abandoned Southampton, VAPJM Sep 2021target 2024
Onshore wind project J163, Tippecanoe County
Onshore wind
100 MWWithdrawn / abandoned Tippecanoe, INMISO Sep 2010target 2014
Battery storage project AG2-324, Loudoun County
Battery storage
100 MWWithdrawn / abandoned Loudoun, VAPJM Mar 2021target 2023
Coal project BHBE G6, Campbell County
Coal
100 MWWithdrawn / abandoned Campbell, SDWest Jul 2006target 2011
Solar + storage project J2825, Panola County
Solar + storage
100 MWWithdrawn / abandoned Panola, MSMISO Sep 2022target 2025
Onshore wind project 32, Whitman County
Onshore wind
100 MWWithdrawn / abandoned Whitman, WAWest Feb 2011target 2012
Solar project J737, Cass County
Solar
100 MWWithdrawn / abandoned Cass, NDMISO Nov 2016target 2019
Kimberlina Solar
Solar
100 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2018
Solar project LGE-GIS-2023-005, Caldwell County
Solar
100 MWWithdrawn / abandoned Caldwell, KYSoutheast Jun 2023target 2026
Battery storage project J2461, Christian County
Battery storage
100 MWWithdrawn / abandoned Christian, ILMISO Sep 2022target 2026
Battery storage project J1709, Grimes County
Battery storage
100 MWWithdrawn / abandoned Grimes, TXMISO Jan 2022target 2025
Solar project J1942, Monroe County
Solar
100 MWWithdrawn / abandoned Monroe, MIMISO Aug 2021target 2023
Solar + storage project 1218, Beaver County
Solar + storage
100 MWWithdrawn / abandoned Beaver, UTWest Apr 2020target 2023
Battery storage project J2016, Daviess County
Battery storage
100 MWWithdrawn / abandoned Daviess, KYMISO Mar 2022target 2025
Fresno Solar
Solar
100 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2014
Onshore wind project GEN-2006-038N014, Madison County
Onshore wind
100 MWWithdrawn / abandoned Madison, NESPP Oct 2006
Solar project 99, Kershaw County
Solar
100 MWWithdrawn / abandoned Kershaw, SCSoutheast Apr 2018target 2020
Onshore wind project G288, Walworth County
Onshore wind
100 MWWithdrawn / abandoned Walworth, WIMISO Jan 2003
Battery storage project J2810, Cerro Gordo County
Battery storage
100 MWWithdrawn / abandoned Cerro Gordo, IAMISO Sep 2022target 2026
Solar project 55, Pima County
Solar
100 MWWithdrawn / abandoned Pima, AZWest Jan 2017target 2018
Willow Solar
Solar
100 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2016
Onshore wind project GEN-2007-011N07, Boone County
Onshore wind
100 MWWithdrawn / abandoned Boone, NESPP Mar 2007target 2010
Battery storage project AH1-615, Allegheny County
Battery storage
100 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2021target 2025
Solar + storage project Company IS, Douglas County
Solar + storage
100 MWWithdrawn / abandoned Douglas, NVWest Sep 2018target 2022
Permian Solar
Solar · SolarCity
100 MWWithdrawn / abandoned ERCOT Jun 2015target 2016
Onshore wind project 48, Adams County
Onshore wind
100 MWWithdrawn / abandoned Adams, WAWest Jan 2016target 2016
Battery storage project 144, Pima County
Battery storage
100 MWWithdrawn / abandoned Pima, AZWest Nov 2022target 2024
Mill Point Solar II
Solar + storage · ConnectGen Montgomery County LLC
100 MWWithdrawn / abandoned Montgomery, NYNYISO Aug 2021
Onshore wind project GEN-2008-034, Murray County
Onshore wind
100 MWWithdrawn / abandoned Murray, OKSPP May 2008target 2010
Gas project G07, Philadelphia County
Gas
100 MWWithdrawn / abandoned Philadelphia, PAPJM Mar 2001
Onshore wind project U2-050, Tazewell County
Onshore wind
100 MWWithdrawn / abandoned Tazewell, VAPJM Jun 2008target 2010
Onshore wind project GEN-2006-038N013, Sioux County
Onshore wind
100 MWWithdrawn / abandoned Sioux, NESPP Oct 2006
Juggernaut
Other · Energy Storage Resources
100 MWWithdrawn / abandoned Waller, TXERCOT May 2019target 2020
Onshore wind project J245, Tuscola County
Onshore wind
100 MWWithdrawn / abandoned Tuscola, MIMISO May 2012target 2018
Solar + storage project Q459, Maricopa County
Solar + storage
100 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2027
Onshore wind project C1-57, Carbon County
Onshore wind
100 MWWithdrawn / abandoned Carbon, WYWest May 2021target 2025
Onshore wind project GI-0710, Hand County
Onshore wind
100 MWWithdrawn / abandoned Hand, SDWest May 2007target 2009
Battery storage project AH2-220, Henry County
Battery storage
100 MWWithdrawn / abandoned Henry, OHPJM Mar 2022target 2026
Page 254 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)