United States βΊ Grid βΊ Interconnection queues βΊ Illinois
SOLAR Β· MISOSolar project J1418, Pulaski County
Solar project J1418, Pulaski County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Pulaski County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedJan 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1418
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Joppa-Joppa North Bus 161kV Substation
- Location
- Pulaski County, Illinois
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- December 2021
- Withdrawn
- January 2020
Location
Marker shows the centre of Pulaski County; the queue data does not give exact sites.
Other requests in Pulaski County
- Battery storage project J3497, Pulaski CountyBattery storage Β· 200 MW Β· in study
- Solar + storage project J3080, Pulaski CountySolar + storage Β· 200 MW Β· in study
- Battery storage project J4137, Pulaski CountyBattery storage Β· 200 MW Β· in study
- Solar + storage project J3254, Pulaski CountySolar + storage Β· 175 MW Β· in study
- Solar project J3276, Pulaski CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project J1830, Pulaski CountySolar + storage Β· 200 MW Β· withdrawn
- Solar project J1799, Pulaski CountySolar Β· 100 MW Β· withdrawn
- Solar project J920, Pulaski CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem