Requests shown1,857519.1 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,857 requests · page 24 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GI-2023-175, Imperial County
Solar + storage
150 MWIn study Imperial, CAWest Apr 2023target 2028
Solar project 16-058, Jefferson County
Solar
150 MWPaused / redesign Jefferson, ORWest Jul 2016target 2018
Solar + storage project 2022-G11, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Aug 2022target 2025
Battery storage project IA-PNM-2023-18, Valencia County
Battery storage
150 MWIn study Valencia, NMWest Sep 2023target 2026
Battery storage project 147, Pima County
Battery storage
150 MWIn study Pima, AZWest Dec 2022target 2026
Solar project G0847, Columbia County
Solar
150 MWIn study Columbia, WAWest Feb 2023target 2024
Onshore wind project C2-49, Converse County
Onshore wind
150 MWIn study Converse, WYWest May 2022target 2026
Solar + storage project BHCT G35, Pueblo County
Solar + storage
150 MWIn study Pueblo, COWest Aug 2022target 2026
Solar + storage project 2022-G10, Pinal County
Solar + storage
150 MWIn study Pinal, AZWest Jul 2022target 2025
Solar + storage project IA-PNM-2023-14, Bernalillo County
Solar + storage
150 MWIn study Bernalillo, NMWest Sep 2023target 2028
Solar + storage project T2-037, Emery County
Solar + storage
150 MWIn study Emery, UTWest Sep 2025target 2028
Solar + storage project C1-40, Yakima County
Solar + storage · CG Yakima County Solar I LLC
150 MWIn study Yakima, WAWest May 2021target 2025
Solar + storage project GI-CS-2025-16, Weld County
Solar + storage
150 MWIn study Weld, COWest Sep 2025target 2029
Battery storage project Q357, Maricopa County
Battery storage
150 MWUnder construction Maricopa, AZWest Sep 2020target 2023
Ea150B
Battery storage
150 MWIn study El Paso, TXWest Jun 2025target 2028
Battery storage project 639, Ada County
Battery storage · Idaho Power Company‚ÄîPower Supply
150 MWAgreement signed Ada, IDWest Feb 2022target 2026
Onshore wind project GI-TC-2024-05, Platte County
Onshore wind
150 MWIn study Platte, WYWest May 2023target 2026
Battery storage project IA-PNM-2025-13, Valencia County
Battery storage
150 MWIn study Valencia, NMWest Mar 2025target 2027
Gas project 465, Stillwater County
Gas
150 MWIn study Stillwater, MTWest Jun 2024target 2029
Solar + storage project 21-11121, Weld County
Solar + storage
150 MWIn study Weld, COWest Nov 2021target 2025
Battery storage project 640, Ada County
Battery storage · Idaho Power Company‚ÄîPower Supply
150 MWPaused / redesign Ada, IDWest Feb 2022target 2026
Other project CLPT G29, Laramie County
Other
150 MWIn study Laramie, WYWest May 2024target 2027
Solar + storage project GI-TC-2024-02, Lincoln County
Solar + storage
150 MWIn study Lincoln, COWest Apr 2024target 2028
Sf150SB
Solar + storage
150 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Solar + storage project Q60, Asotin County
Solar + storage
150 MWPaused / redesign Asotin, WAWest
Battery storage project 27, Sacramento County
Battery storage
150 MWIn study Sacramento, CAWest Oct 2022target 2027
Solar + storage project IA-PNM-2021-09, Bernalillo County
Solar + storage · NextEra Energy
150 MWAgreement signed Bernalillo, NMWest Jul 2021target 2025
Huning Energy
Solar
150 MWIn study Valencia, NMWest Jul 2021target 2025
WA_150SB Project
Solar + storage
150 MWPaused / redesign Bernalillo, NMWest Sep 2021target 2026
Solar project PIS027, Utah County
Solar
150 MWIn study Utah, UTWest Jul 2022target 2025
Corazon Energy Storage
Battery storage
150 MWAgreement signed Bernalillo, NMWest Jul 2021target 2024
Onshore wind project GI-TC-2024-06, Platte County
Onshore wind
150 MWIn study Platte, WYWest May 2023target 2026
Battery storage project T2-072, Siskiyou County
Battery storage
150 MWIn study Siskiyou, CAWest Sep 2025target 2027
Solar + storage project 2023-G2
Solar + storage
150 MWIn study West Nov 2022target 2026
Battery storage project IA-PNM-2021-16, Sandoval County
Battery storage · EsVolta Development
150 MWAgreement signed Sandoval, NMWest Jul 2021target 2024
Solar project 2023-G3
Solar
150 MWIn study West Nov 2022target 2026
Solar + storage project Q463, Maricopa County
Solar + storage
150 MWIn study Maricopa, AZWest Mar 2022target 2024
Battery storage project Q299, Maricopa County
Battery storage
150 MWAgreement signed Maricopa, AZWest Mar 2019target 2023
Solar project GI-2024-03, Adams County
Solar
150 MWIn study Adams, COWest Apr 2024target 2029
Solar project Company IG, Humboldt County
Solar
150 MWAgreement signed Humboldt, NVWest Mar 2018target 2023
Battery storage project 122, Pinal County
Battery storage
150 MWIn study Pinal, AZWest May 2022target 2026
Solar + storage project 60, Asotin County
Solar + storage
150 MWPaused / redesign Asotin, WAWest Jun 2018target 2025
Solar + storage project GI-DISIS-2021-04, Otero County
Solar + storage
150 MWAgreement signed Otero, NMWest May 2021target 2028
Solar + storage project GI-CS-2025-22, Huerfano County
Solar + storage
150 MWIn study Huerfano, COWest Sep 2025target 2030
Ve-DL-150SB
Solar + storage
150 MWIn study Dona Ana, NMWest Jun 2025target 2028
Solar + storage project 716, Ada County
Solar + storage
150 MWIn study Ada, IDWest May 2023target 2028
Battery storage project 22-110, Marion County
Battery storage
150 MWIn study Marion, ORWest Apr 2022target 2028
Solar + storage project 2023-G6, Mohave County
Solar + storage
150 MWIn study Mohave, AZWest May 2023target 2027
Battery storage project 25-00435, Storey County
Battery storage
150 MWIn study Storey, NVWest Jul 2025target 2029
Globemallow Solar
Solar + storage
150 MWAgreement signed Santa Fe, NMWest Jul 2021target 2024
Page 24 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)