Solar + storage project GI-CS-2025-22, Huerfano County

Solar + storage project GI-CS-2025-22, Huerfano County is a 150 MW solar + storage request in interconnection study in the West interconnection queue, in Huerfano County, Colorado, connecting to Tri-State Generation and Transmission Association.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-CS-2025-22
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Walsenburg - Comanche 230kV Line
Location
Huerfano County, Colorado
Technology
Solar: 150 MW · Battery
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
Cluster Study
Queue status
Active
Entered queue
29 September 2025
Proposed online date
February 2030

Location

Marker shows the centre of Huerfano County; the queue data does not give exact sites.

Power plants in Colorado · Transmission lines in Colorado

Other requests in Huerfano County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem