United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

ONSHORE WIND Β· WEST

Onshore wind project GI-2008-2, Huerfano County

Onshore wind project GI-2008-2, Huerfano County is a 300 MW onshore wind request withdrawn in the West interconnection queue, in Huerfano County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2008 (completed)
  2. Withdrawn / abandonedSep 2011 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2008-2
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Comanche Substation
Location
Huerfano County, Colorado
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study complete System Impact Study underway Request Withdrawn 9/16/11
Queue status
Withdrawn
Entered queue
5 March 2008
Proposed online date
July 2009
Withdrawn
September 2011

Location

Marker shows the centre of Huerfano County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Huerfano County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem