Withdrawn queue requests in the USA (2020 requests) โ€” page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests ยท page 23 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Solar
Solar
40.0 MWWithdrawn / abandoned Androscoggin, MEISO-NE Mar 2020target 2022
Bellefontaine PV and BESS Project
Solar + storage ยท Hodson GreenDefine Blue Jacket LLC
40.0 MWWithdrawn / abandoned Logan, OHPJM Sep 2020target 2023
Solar project AF2-074, Gates County
Solar
40.0 MWWithdrawn / abandoned Gates, NCPJM Jan 2020target 2024
Solar + storage project 1219, Gilliam County
Solar + storage
40.0 MWWithdrawn / abandoned Gilliam, ORWest Apr 2020target 2023
Solar + storage project AF2-232, Columbia County
Solar + storage
40.0 MWWithdrawn / abandoned Columbia, PAPJM Mar 2020target 2021
Solar + storage project AG1-277, Luzerne County
Solar + storage ยท LU-Tank LLC
40.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2020target 2022
Solar project J1600, Meade County
Solar
40.0 MWWithdrawn / abandoned Meade, KYMISO Jun 2020target 2022
Solar project 126078, Laurens County
Solar
40.0 MWWithdrawn / abandoned Laurens, SCSoutheast Mar 2020
Colorado Bend I Repower
Gas
40.0 MWWithdrawn / abandoned Wharton, TXERCOT Mar 2020
Battery storage project AG1-150, Accomack County
Battery storage
40.0 MWWithdrawn / abandoned Accomack, VAPJM Sep 2020target 2021
Solar + storage project 1214, Crook County
Solar + storage
40.0 MWWithdrawn / abandoned Crook, ORWest Apr 2020target 2024
Battery storage project GEN-2020-SR1, Beckham County
Battery storage
40.0 MWWithdrawn / abandoned Beckham, OKSPP Aug 20202024
Scout Energy Storage
Battery storage
40.0 MWWithdrawn / abandoned Accomack, VAPJM Jan 2020target 2021
Battery storage project AF2-394, Adams County
Battery storage ยท Bison Meadows Wind Project, LLC
40.0 MWWithdrawn / abandoned Adams, ILPJM Mar 2020target 2024
Solar project AG1-458, Washington County
Solar
40.0 MWWithdrawn / abandoned Washington, MDPJM Sep 2020target 2023
Solar project AF2-067, Preble County
Solar
40.0 MWWithdrawn / abandoned Preble, OHPJM Jan 2020target 2022
Solar
Solar
40.0 MWWithdrawn / abandoned Hampshire, MAISO-NE Jun 2020target 2023
Solar project AF2-094, Huntington County
Solar
40.0 MWWithdrawn / abandoned Huntington, INPJM Feb 2020target 2022
Bartonsville Energy Facility
Solar
40.0 MWWithdrawn / abandoned Frederick, VAPJM Sep 2020target 2023
Onshore wind project J1761, Barnes County
Onshore wind
39.0 MWWithdrawn / abandoned Barnes, NDMISO Jun 2020target 2023
Onshore wind project J1801, Story County
Onshore wind
39.0 MWWithdrawn / abandoned Story, IAMISO Jun 2020target 2023
Solar project J1784, Henry County
Solar
39.0 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2023
Onshore wind project J1728, Story County
Onshore wind
39.0 MWWithdrawn / abandoned Story, IAMISO Jun 2020target 2023
Solar project AG1-067, Barren County
Solar
38.0 MWWithdrawn / abandoned Barren, KYPJM Jul 2020target 2023
Solar project AF2-127, Defiance County
Solar
38.0 MWWithdrawn / abandoned Defiance, OHPJM Feb 2020target 2022
Other project 132808, Cumberland County
Other ยท Duke Energy Progress, LLC
38.0 MWWithdrawn / abandoned Cumberland, NCSoutheast Sep 2020
Solar project 165980, Laurens County
Solar
37.5 MWWithdrawn / abandoned Laurens, SCSoutheast Mar 2020
Onshore wind project J1767, Hancock County
Onshore wind
37.0 MWWithdrawn / abandoned Hancock, IAMISO Jun 2020target 2023
Solar project AF2-220, Pulaski County
Solar
37.0 MWWithdrawn / abandoned Pulaski, VAPJM Mar 2020target 2023
Hydro project AG1-292, Beaver County
Hydro
36.6 MWWithdrawn / abandoned Beaver, PAPJM Sep 2020target 2023
Solar + storage project Q330, Yuma County
Solar + storage
36.0 MWWithdrawn / abandoned Yuma, AZWest Mar 2020target 2022
Solar project AG1-356, Somerset County
Solar
36.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2020target 2023
Gas project AG1-094, Prince George's County
Gas
35.3 MWWithdrawn / abandoned Prince George's, MDPJM Aug 2020target 2021
Battery storage project AG1-442, Bertie County
Battery storage ยท RWE Solar Development, LLC
35.0 MWWithdrawn / abandoned Bertie, NCPJM Sep 2020target 2023
Battery storage project AG1-443, Bertie County
Battery storage ยท RWE Solar Development, LLC
35.0 MWWithdrawn / abandoned Bertie, NCPJM Sep 2020target 2023
Solar project 147, Clarendon County
Solar
35.0 MWWithdrawn / abandoned Clarendon, SCSoutheast May 2020target 2025
Battery storage project AG1-455, Crawford County
Battery storage
35.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2020target 2022
Solar + storage project AG1-550, Fluvanna County
Solar + storage
35.0 MWWithdrawn / abandoned Fluvanna, VAPJM Sep 2020target 2023
Solar project AG1-208, Montgomery County
Solar
35.0 MWWithdrawn / abandoned Montgomery, KYPJM Sep 2020target 2022
Solar project AG1-327, Franklin County
Solar
35.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2020target 2023
Wood River - NG WRI DG Area Study #2 >5 MW
Solar
34.4 MWWithdrawn / abandoned Washington, RIISO-NE Aug 2020target 2025
Onshore wind project J1776, Osceola County
Onshore wind
34.0 MWWithdrawn / abandoned Osceola, IAMISO Jun 2020target 2023
Onshore wind project J1727, Hancock County
Onshore wind
33.8 MWWithdrawn / abandoned Hancock, IAMISO Jun 2020target 2023
Eversource Group @ Tremont Substation 713
Solar + storage
33.7 MWWithdrawn / abandoned Plymouth, MAISO-NE Apr 2020target 2023
XE RHODA Solar
Solar ยท Milam 2 Solar
33.7 MWWithdrawn / abandoned Milam, TXERCOT Jul 2020target 2024
Onshore wind project J1763, Cavalier County
Onshore wind
33.0 MWWithdrawn / abandoned Cavalier, NDMISO Jun 2020target 2023
Solar + storage project AG2-035, Salem County
Solar + storage ยท ACE Development Company, LLC
33.0 MWWithdrawn / abandoned Salem, NJPJM Nov 2020target 2021
Iceberg Energy Storage
Battery storage
31.8 MWWithdrawn / abandoned Monterey, CACAISO Apr 2020target 2022
Angels Creek
Battery storage ยท Angels Creek LLC
31.7 MWWithdrawn / abandoned ERCOT Jun 2020target 2026
Santos Solar
Solar
31.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2020target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)